Flood Control and Drainage24CC0180

CONSTRUCTION/IMPROVEMENT OF FLOOD MITIGATION STRUCTURE AT SANTO ROSARIO, MALOLOS CITY, BULACAN

CONSTRUCTION/IMPROVEMENT OF FLOOD MITIGATION STRUCTURE AT SANTO ROSARIO, MALOLOS CITY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱74,111,429.79. Status: Past target date (DPWH On-Going). Contractor on record: FERDSTAR BUILDERS INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000335

₱29,019,605.00 · FY2024

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

139 projects · ₱8.9B total · 1 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS-CONSTRUCTION OF RING DIKE WITH PUMPING STATION (PHASE 2 & 4), MACABEBE-MASANTOL, PROVINCE OF PAMPANGA

Region III, Region III

2024₱354.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 3, PROVINCE OF PAMPANGA

Region III, Region III

2020₱193.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ABACAN RIVER, DIKING AND SLOPE PROTECTION WORKS-PHASE 2, MEXICO, PAMPANGA

Region III, Region III

2025₱170.1M
Past target date (DPWH On-Going)
No sat.

PASIG-MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, CONTRACT PACKAGE NO. 4-B, RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 15+700 TO STA. 15+957 (PHASE 2), RIGHT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2022₱148.4M
Reported complete (100% progress, DPWH status On-Going)

Flood Control Works - Diking/Slope Protection of Pasig-Potrero River, Bacolor and Porac, Pampanga

PORAC (PAMPANGA), PAMPANGA, Region III

2023₱144.8M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION), PACKAGE 5, PROVINCE OF PAMPANGA

Region III, Region III

2020₱144.7M
Reported complete (DPWH)
View all 139 projects →

4. Implementation

Contract Amount

₱74,111,429.79

Progress

Past target date (DPWH On-Going)

Start Date

February 28, 2024

Target End

December 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.