Construction of Flood Mitigation Structure22GF0047

Construction of Guimbal Shoreline Protection, Guimbal, Iloilo

Construction of Guimbal Shoreline Protection, Guimbal, Iloilo is a DPWH-tracked public work in GUIMBAL (ILOILO), ILOILO, Region VI. Reported contract value: ₱9,703,498.97. Status: Reported complete (DPWH). Contractor on record: GOLDEN ROADRUNNER INTERNATIONAL CORP. Figures trace to sumbong.

GUIMBAL (ILOILO), ILOILO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Joaquin Flood Mitigation Shoreline Protection, Barangay Purok 1, San Joaquin, Iloilo
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0011484

₱20,590.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002720

₱615,831,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱9,703,498.97

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

October 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.