Flood Control and Drainage20DD0253

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, FLOOD CONTROL AND DRAINAGE, DRAINAGE / PROTECTION WORKS, CONSTRUCTION/ REHABILITATION/ IMPROVEMENT OF DRAINAGE SYSTEM AT BRGY. SABANG, LIP

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, FLOOD CONTROL AND DRAINAGE, DRAINAGE / PROTECTION WORKS, CONSTRUCTION/ REHABILITATION/ IMPROVEMENT OF DRAINAGE SYSTEM AT BRGY. SABANG, LIP is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱9,495,121.25. Status: Reported complete (DPWH). Contractor on record: MEGAJES CONST CORP. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Structure at Brgy. Tambo, Lipa City, Batangas
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-20-0008301

₱127,660,800.00 · FY2020

Released to Batangas 4th DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

36 projects · ₱426.6M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, M

Batangas 4th DEO, Region IV-A

2024₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF QUILO-QUILO-SAN CARLOS

Batangas 4th DEO, Region IV-A

2024₱28.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAWI AND BANABA CREEK, PAD

Batangas 4th DEO, Region IV-A

2024₱28.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (CHED), LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱19.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT BARANGAY SABANG, LIPA CITY BATANGAS

Batangas 4th DEO, Region IV-A

2024₱19.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN BAGONG POOK ELEMENTARY SCHOOL, BRGY. BAGONG POOK, ROSARIO, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱16.9M
Past target date (DPWH On-Going)
View all 36 projects →

4. Implementation

Contract Amount

₱9,495,121.25

Progress

Reported complete (DPWH)

Start Date

December 3, 2020

Target End

March 2, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.