Roads25CH0055

ASSET PRESERVATION PROGRAM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - JOSE ABAD SANTOS AVE. (JASA) - K0089+000 - K0089+440, LUBAO, PAMPANGA

ASSET PRESERVATION PROGRAM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - JOSE ABAD SANTOS AVE. (JASA) - K0089+000 - K0089+440, LUBAO, PAMPANGA is a DPWH-tracked public work in Pampanga 2nd DEO, Region III. Reported contract value: ₱14,579,667.53. Status: Past target date (DPWH On-Going). Contractor on record: TRI-TON ENGINEERING SERVICES. Figures trace to dpwh.

Pampanga 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Santa Monica, Sasmuan, Pampanga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-25-0016156

₱1,751,838.00 · FY2025

Released to Division of Panabo City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25CH0055

₱14,579,667.53 · TRI-TON ENGINEERING SERVICES

Contractor

C

18 projects · ₱192.2M total · 0 flags

4. Implementation

Contract Amount

₱14,579,667.53

Progress

Past target date (DPWH On-Going)

Start Date

June 4, 2025

Target End

January 29, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.