Roads23PI0029

CSSP-ROLL-IT: BATO-CUBA-BALICANAO-PUA-MANKINGAO ROAD CONNECTING BATO AND MANKINGAO IN SUPPORT OF FOOD/VEGETABLE PROCESSING AND COFFEE INDUSTRIES, BRGY. SADSADAN AND BRGY. MONAMON SUR, BAUKO, MOUNTAIN PROVINCE

CSSP-ROLL-IT: BATO-CUBA-BALICANAO-PUA-MANKINGAO ROAD CONNECTING BATO AND MANKINGAO IN SUPPORT OF FOOD/VEGETABLE PROCESSING AND COFFEE INDUSTRIES, BRGY. SADSADAN AND BRGY. MONAMON SUR, BAUKO, MOUNTAIN PROVINCE is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱2,450,000.00. Status: Reported complete (DPWH). Contractor on record: MOUNTAIN HORIZON BUILDER. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Chico River Flood Control, Tamog - o Section at Sitio Tamog - o in Barangay Monamon Norte, Bauko, Mountain Province
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0024870

₱60,191.00 · FY2023

Released to Davao de Oro State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,450,000.00

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

March 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.