Bridges18IK0062

WIDENING OF PERMANENT BRIDGES, MANUNCA BRIDGE ALONG DAANG MAHARLIKA

WIDENING OF PERMANENT BRIDGES, MANUNCA BRIDGE ALONG DAANG MAHARLIKA is a DPWH-tracked public work in Samar 2nd DEO, Region VIII. Reported contract value: ₱22,781,590.91. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FRD CONST. Figures trace to dpwh.

Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱22,781,590.91

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 18, 2018

Target End

January 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.