Bridges21DE0086

LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF BRIDGE, BARANGAY TALON, SAN LUIS, BATANGAS

LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF BRIDGE, BARANGAY TALON, SAN LUIS, BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱14,850,000.00. Status: Reported complete (DPWH). Contractor on record: ABLB CONST SERVICES. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay San Mateo, San Pascual, Batangas
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱407,327,000.00 · FY2021

Released to Batangas 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

32 projects · ₱251.0M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF STREETLIGHTS AT PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2023₱28.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE- SECONDARY ROADS, ROSARIO - SAN JUAN ROAD K0124 + 000 - K0124 + 872

Batangas 4th DEO, Region IV-A

2022₱24.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT USING STONE MASONRY, LIPA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱19.2M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OOUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE

Batangas 4th DEO, Region IV-A

2021₱14.8M
Reported complete (DPWH)
No sat.

CONCRETING OF BARANGAY PANSOL FMR, BARANGAY PANSOL, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱14.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY SICO I, AND BARANGAY LAIYA APLAYA, SAN JUAN, BA

Batangas 4th DEO, Region IV-A

2024₱10.6M
Reported complete (DPWH)
View all 32 projects →

4. Implementation

Contract Amount

₱14,850,000.00

Progress

Reported complete (DPWH)

Start Date

February 3, 2021

Target End

July 2, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.