Roads25JE0051

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) CONSTRUCTION OF ROAD, NRJ LITAPAN- BAG-ONG ARIOSA- BAG-ONG GUTLANG, MOLAVE, ZAMBOANGA DEL SUR

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) CONSTRUCTION OF ROAD, NRJ LITAPAN- BAG-ONG ARIOSA- BAG-ONG GUTLANG, MOLAVE, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 1st DEO, Region IX. Reported contract value: ₱29,369,688.26. Status: Past target date (DPWH On-Going). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga del Sur 1st DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Salug Diut River, Barangay Colo, Molave, Zamboanga del Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-25-0010716

₱1,477,577.00 · FY2025

Released to Davao del Sur District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱29,369,688.26

Progress

Past target date (DPWH On-Going)

Start Date

April 1, 2025

Target End

November 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.