Water Provision and Storage23BC0153

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS)

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS) is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱2,285,137.03. Status: Reported complete (DPWH). Contractor on record: V S LAUNGAYAN HARDWARE AND CONST SUPPLY. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Centro Lasam Flood Control Along Zinundungan River, Lasam, Cagayan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-23-0019198

₱23,364,577.00 · FY2023

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

93 projects · ₱517.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF ROAD, BARANGAY GUIDDAM, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2024₱29.6M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BRGY. SAN JULIAN FMR, BRGY, SAN JULIAN, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2022₱29.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OS MOTORPOOL, DPWH CAGAYAN @ND DEO, LIBERTAD, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2024₱24.2M
Past target date (DPWH On-Going)
No sat.

LOCAL ROADS AND BRIDGES: CONSTRUCTION OF ROAD WITH DRAINAGE CANAL FROM CALVARIO CENTRO 02 TO WACA, BRGY. SAN JUAN, STA. PRAXEDES, CAGAYAN STA. 0+000-STA.0+460 (SEC 1) STA.0+000-STA.0+320 (SEC 2)

Cagayan 2nd DEO, Region II

2019₱19.2M
Reported complete (DPWH)
No sat.

CSSP- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES ( ROLL-IT), STO. TOMAS BARANGAY ROAD LEADING TO MANILA NORTH ROAD (MNR) LEADING TO AGRIBUSINESS INDUSTRY (AQUATIC RESOURCES, LIVESTOCK, VEGETABLES AND COCONUT)

Cagayan 2nd DEO, Region II

2021₱18.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES-MACUGAY BARANGAY ROAD LEADING TO MANILA NORTH ROAD LEADING TO AGRIBUSINESS INDUSTRY, MACUGAY, GUIDDAM, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2020₱16.7M
Reported complete (DPWH)
View all 93 projects →

4. Implementation

Contract Amount

₱2,285,137.03

Progress

Reported complete (DPWH)

Start Date

May 5, 2023

Target End

August 2, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.