Flood Control and Drainage24IE0054

CONSTRUCTION OF RIVER CONTROL STRUCTURE, BARANGAY HINABUYAN, VILLABA, LEYTE

CONSTRUCTION OF RIVER CONTROL STRUCTURE, BARANGAY HINABUYAN, VILLABA, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱34,303,498.87. Status: Past target date (DPWH On-Going). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Jalas, Villaba, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-24-0013236

₱1,711,243.00 · FY2024

Released to Matalam High School (Poblacion) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

692 projects · ₱17.7B total · 35 flags

4. Implementation

Contract Amount

₱34,303,498.87

Progress

Past target date (DPWH On-Going)

Start Date

April 23, 2024

Target End

January 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.