ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOODMANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF REVETMENT ALONG ILANG-ILANG RIVER, PHASE V, BRGY. BACAO II
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOODMANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF REVETMENT ALONG ILANG-ILANG RIVER, PHASE V, BRGY. BACAO II is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱39,199,998.09. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TRIPLE 8 CONST. Figures trace to dpwh.
Total Contract Cost