Buildings and Facilities25DB0018

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY SABANG, TUY, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY SABANG, TUY, BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱1,920,509.00. Status: Past target date (DPWH On-Going). Contractor on record: HAUSLAND CONST. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Barangay Malibu, Tuy, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-25-0017089

₱1,741,273.00 · FY2025

Released to Carigara National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

234 projects · ₱9.5B total · 1 flags

Other projects by this contractor

No sat.

CONST OF FOUR (4) STOREY - ONE HUNDRED (100) CLASSROOM SB @ TAGAYTAY CITY, CAVITE

Cavite 2nd DEO, Region IV-A

2018₱208.9M
Reported complete (DPWH)
No sat.

CONST OF MPB (TENEMENT HOUSING), BRGY MAITIM EAST, TAGAYTAY CITY

Cavite 2nd DEO, Region IV-A

2023₱181.4M
Past target date (DPWH On-Going)
No sat.

FY 2018 DPWH INFRASTRUCTURE PROGRAM LOCAL PROGRAM LOCAL INFRASTRUCTURE PROGRAMNATIONAL ROADS AND BRIDGE NATIONAL ROADSROAD OPENING / CONSTRUCTION OF TAGAYTAY BYPASS ROAD, TAGAYTAY CITY, CAVITE

Region IV-A, Region IV-A

2018₱144.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - JUANITO R. REMULLA, SR. RD - K0035 + (-008) - K0035 + 109, K0035 + (

Cavite 3rd DEO, Region IV-A

2023₱127.8M
Past target date (DPWH On-Going)
No sat.

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS / NEW ROADS GENERAL AGUINALDO-MAGALLANES -NASUGBU ROAD (EAST - WEST ROAD), PACKAGE 3, MAGALLANES-GEN. AGUINALDO SECT., CAVITE

Region IV-A, Region IV-A

2021₱127.0M
Past target date (DPWH On-Going)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM NETWORK DEV'T. PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS GEN. AGUINALDO- MAGALLANES- NASUGBU ROAD (EAST- WEST ROAD), AMADEO SECT., CAVITE

Region IV-A, Region IV-A

2020₱125.4M
Reported complete (DPWH)
View all 234 projects →

4. Implementation

Contract Amount

₱1,920,509.00

Progress

Past target date (DPWH On-Going)

Start Date

February 18, 2025

Target End

May 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.