Construction of Flood Mitigation Structure22FC0182

Construction of Daet River Control Structure, Brgy. 1 Section Barangay 1, Daet, Camarines Norte

Construction of Daet River Control Structure, Brgy. 1 Section Barangay 1, Daet, Camarines Norte is a DPWH-tracked public work in DAET (CAPITAL) (CAMARINES NORTE), CAMARINES NORTE, Region V. Reported contract value: ₱28,511,229.65. Status: Reported complete (DPWH). Contractor on record: EUS CONST. Figures trace to sumbong.

DAET (CAPITAL) (CAMARINES NORTE), CAMARINES NORTE, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱42,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Talisay River Flood Control Structure, Brgy. Binanuan, Talisay, Camarines Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-22-0011213

₱16,995,909.00 · FY2022

Released to Camarines Norte District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002900

₱1,325,575,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002430

₱43,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

193 projects · ₱9.1B total · 7 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MADUNGON RIVER, BARANGAY STA. ANA, SOLSONA, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.4M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱140.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL IN BRGY. SAN ANTONIO, LABO-BRGY. FABRICA (MATOG

Region V, Region V

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱140.3M
Past target date (DPWH On-Going)
View all 193 projects →

4. Implementation

Contract Amount

₱28,511,229.65

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

September 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.