Unprogrammed Appropriations 202424F00507

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL IN BRGY. SAN ANTONIO, LABO-BRGY. FABRICA (MATOG

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL IN BRGY. SAN ANTONIO, LABO-BRGY. FABRICA (MATOG is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱140,406,339.00. Status: Past target date (DPWH On-Going). Contractor on record: EUS CONST. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24F00507

₱140,406,339.00 · EUS CONSTRUCTION

Contractor

B

193 projects · ₱9.1B total · 7 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MADUNGON RIVER, BARANGAY STA. ANA, SOLSONA, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.4M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱140.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱140.3M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY MALATAP, LABO, CAMARIN

Region V, Region V

2024₱115.8M
Reported complete (DPWH)
View all 193 projects →

4. Implementation

Contract Amount

₱140,406,339.00

Progress

Past target date (DPWH On-Going)

Start Date

March 28, 2025

Target End

December 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.