Bridges22B00039

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: IMPROVEMENT OF CAPACITY OF PROVINCIAL ROADS (PROVINCIAL BRIDGES FOR ECONOMIC DEVELOPMENT-PROBED) - REPLACEMENT OF STO. TOMAS BRIDGE ALONG LA PAZ-SALVACION-STO. TOMAS ROAD

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: IMPROVEMENT OF CAPACITY OF PROVINCIAL ROADS (PROVINCIAL BRIDGES FOR ECONOMIC DEVELOPMENT-PROBED) - REPLACEMENT OF STO. TOMAS BRIDGE ALONG LA PAZ-SALVACION-STO. TOMAS ROAD is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱40,152,914.60. Status: Reported complete (DPWH). Contractor on record: A P D CONST INC FORMERLY: APD CONST. Figures trace to dpwh.

Region II, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

355 projects · ₱12.1B total · 1 flags

Other projects by this contractor

No sat.

NETWORK DEV'T PROGRAM: CONST'N OF MISSING LINKS/NEW ROADS JCT. VICTORIA-MADDELA-ALICIA-KASIBU, NUEVA VIZCAYA ROAD, QUIRINO, STA. 0+000-STA. 4+500, AGLIPAY, QUIRINO

Region II, Region II

2018₱185.7M
Reported complete (DPWH)
No sat.

OO 1. NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROAD-JCT. ABBAG-GUINGIN BOUNDARY ROAD (BUCAO-LA CONWAP SECTION) QUIRINO, STA. 0+000-STA. 3+040 (CONCRETING, STA. 3+320-STA. 4+240 (OPENING), QUIRINO LONE DISTRICT

Region II, Region II

2018₱166.7M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARITAO-QUIRINO ROAD, PACKAGE 1, QUIRINO

Region II, Region II

2024₱158.9M
Reported complete (DPWH)
No sat.

MFO 1: NAT'L ROAD NETWORK SERVICES: NETWORK DEV'T: CONST'N OF MISSING GAPS CONNECTING NAT'L ROADS INCLUDING ROW, JCT. ABBAG-GUINGIN BDRY. ROAD (BUCAO-LA CONWAP SECTION) INCLUDING SLOPE PROTECTION, STA. 000+000-STA.001+680, STA. 002+220-STA.003+770, NAGTIP

Region II, Region II

2017₱142.0M
Reported complete (DPWH)
No sat.

MFO 3:MAINTENANCE AND CONSTRUCTION SERVICES OF OTHER INFRASTRUCTURES: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS-TO DECLARED TOURISM DESTINATIONS-NRJ GUNDAWAY-SUSONG DALAGA, ZAMORA SAN MARCOS-

Region II, Region II

2017₱141.7M
Reported complete (DPWH)
No sat.

MFO 1: NAT'L RD. NETWORK SERVICES: RD. UPGRADING(UNPAVED TO PAVED) BASED ON GRAVEL RD. STRATEGIES, TRAFIC BENCHMARK FOR UPGRADING TO PAVED RD. STANDARD(HDM 4-PROJ.ANALYSIS),TERTIARY RD., JCT. ABBAG-GUINGIN BDRY. RD.

Region II, Region II

2017₱133.8M
Reported complete (DPWH)
View all 355 projects →

4. Implementation

Contract Amount

₱40,152,914.60

Progress

Reported complete (DPWH)

Start Date

March 28, 2022

Target End

October 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.