Roads24CD0090

CONSTRUCTION MACAIBAN PATAG ROAD DIKE PHASE 3, STA. MARIA, BULACAN

CONSTRUCTION MACAIBAN PATAG ROAD DIKE PHASE 3, STA. MARIA, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱72,352,142.84. Status: Reported complete (DPWH). Contractor on record: 729 CONST INC FORMERLY 722 CONST INC. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sta. Maria River, Sta. 04 + 900 - Sta. 05 + 050 ( Poblacion - Macaiban Section ) , Santa Maria, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0018833

₱7,150,000.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

231 projects · ₱7.1B total · 0 flags

4. Implementation

Contract Amount

₱72,352,142.84

Progress

Reported complete (DPWH)

Start Date

March 14, 2024

Target End

February 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.