Buildings and Facilities18MB0058

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (UPPER TAMBLER 1 E/S), FATIMA, GENERAL SANTOS CITY, SOUTH COTABATO

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (UPPER TAMBLER 1 E/S), FATIMA, GENERAL SANTOS CITY, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱1,845,400.28. Status: Reported complete (DPWH). Contractor on record: A L ACHARON CONST AND SUPPLY 33068. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,845,400.28

Progress

Reported complete (DPWH)

Start Date

May 14, 2018

Target End

August 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.