Roads22MB0128

CONCRETING OF PUROK 7 TO PUROK 20, BRGY. MABUHAY FMR PHASE III, BRGY. MABUHAY, GENERAL SANTOS CITY

CONCRETING OF PUROK 7 TO PUROK 20, BRGY. MABUHAY FMR PHASE III, BRGY. MABUHAY, GENERAL SANTOS CITY is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱11,863,846.81. Status: Reported complete (DPWH). Contractor on record: A L ACHARON CONST AND SUPPLY. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bolok Creek, Koronadal City, South Cotabato
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-22-0000690

₱177,364,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱11,863,846.81

Progress

Reported complete (DPWH)

Start Date

October 20, 2022

Target End

February 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.