Roads18K00226

CLUSTER 22 CONST. OF MISSING LINKS/ NEW ROADS, BUKIDNON

CLUSTER 22 CONST. OF MISSING LINKS/ NEW ROADS, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱550,992,963.43. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱550,992,963.43

Progress

Reported complete (DPWH)

Start Date

July 12, 2018

Target End

February 20, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.