Construction of Flood Mitigation Structure23NA0001

Construction of Guihao-an River Bank Protection along Guihao-an Bridge with Rechannelization, Buenavista, Agusan del Norte

Construction of Guihao-an River Bank Protection along Guihao-an Bridge with Rechannelization, Buenavista, Agusan del Norte is a DPWH-tracked public work in BUENAVISTA (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII. Reported contract value: ₱96,498,619.17. Status: Reported complete (DPWH). Contractor on record: ADFIL CORP. Figures trace to sumbong.

BUENAVISTA (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Agay River, Brgy. Balang-Balang RTR, Agusan del Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-23-0020432

₱2,813,136.00 · FY2023

Released to 0000000 Surigao del Norte - State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,498,619.17

Progress

Reported complete (DPWH)

Start Date

February 16, 2023

Target End

October 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.