Buildings and Facilities15MD0253

CONSTRUCTION OF MP BULDING, BRGY. BALIKI, MIDSAYAP, COTABATO

CONSTRUCTION OF MP BULDING, BRGY. BALIKI, MIDSAYAP, COTABATO is a DPWH-tracked public work in Cotabato 1st DEO, Region XII. Reported contract value: ₱1,871,228.80. Status: Reported complete (DPWH). Contractor on record: ACJ CONST RESOURCES. Figures trace to dpwh.

Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0012328

₱5,462,624.00 · FY2016

Released to Eastern Visayas Centers for Health Development To (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,871,228.80

Progress

Reported complete (DPWH)

Start Date

January 28, 2016

Target End

April 15, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.