Buildings and Facilities25OB0090

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SANTA LUCIA, PASIG CITY

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SANTA LUCIA, PASIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱9,795,906.36. Status: Reported complete (DPWH). Contractor on record: GARBIA STRUCTURAL AND GEOTECHNICAL SOLUTIONS. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0011891

₱631,595.00 · FY2025

Released to Regional Office - XI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Possible match · 74%

Contract ID 21CSOB0015-Contract Name SUB-SURFACE S

₱274,180.20 · GARBIA STRUCTURAL AND GEOTECHNICAL SOLUTIONS

Possible match · 73%

Contract ID No. 019CSOB0028-Sub-Surface Soil Exp

₱865,158.50 · GARBIA STRUCTURAL AND GEOTECHNICAL SOLUTIONS

Possible match · 73%

Contract ID No. 019CSOB0012-Sub-Surface Soil Exp

₱398,470.00 · GARBIA STRUCTURAL AND GEOTECHNICAL SOLUTIONS

Possible match · 71%

24CSOB0017 Sub-Surface Soil Exploration for the Co

₱1,532,370.00 · GARBIA STRUCTURAL AND GEOTECHNICAL SOLUTIONS

Possible match · 69%

24CSOB0003 Sub-Surface Soil Exploration for the Co

₱256,101.30 · GARBIA STRUCTURAL AND GEOTECHNICAL SOLUTIONS

Contractor

1 projects · ₱9.8M total · 0 flags

4. Implementation

Contract Amount

₱9,795,906.36

Progress

Reported complete (DPWH)

Start Date

February 17, 2025

Target End

May 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.