Roads22BA0004

CONSTRUCTION OF MISSING LINKS/NEW ROADS: SAN VICENTE-SAVIDUG-CHAVAYAN-SUMNANGA-NAKANMUAN ROAD - PACKAGE 4

CONSTRUCTION OF MISSING LINKS/NEW ROADS: SAN VICENTE-SAVIDUG-CHAVAYAN-SUMNANGA-NAKANMUAN ROAD - PACKAGE 4 is a DPWH-tracked public work in Batanes DEO, Region II. Reported contract value: ₱19,478,543.62. Status: Reported complete (DPWH). Contractor on record: R D MANDANAS CONST. Figures trace to dpwh.

Batanes DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Savang-Aksung, Barangay Nakanmuan, Sabtang, Batanes
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004266

₱1,088,695.00 · FY2022

Released to Bataan School of Fisheries (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

107 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (KALINGA PROVINCIAL HOSPITAL OR-DR COMPLEX), KPH COMPOUND, BULANAO, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2018₱77.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (GOVERNOR ROY PADILLA SR. MEMORIAL STADIUM), CAMARINES NORTE, JOSE PANGANIB

Region V, Region V

2024₱57.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY (TATAG NG INPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF QUIRINO PROVINCIAL MOBILE FORCE COMPANY

Region II, Region II

2021₱54.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF THREE (3) STOREY, TWO (2) REGULAR WORKSHOP, TWO (2) SCIENCE LABORATORY, TWO (2) ICT LABORATORY BUILDING (PHASE I), BARCELONITA, CABUSAO, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2019₱51.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF THREE(3) UNIT TWO(2) STOREY TEN(10) CLASSROOM AT P. ROMAN NATIONAL HIGH SCHOOL, PILAR, BATAAN

Bataan 2nd DEO, Region III

2016₱44.0M
Reported complete (DPWH)
No sat.

CLUSTER: CONSTRUCTION OF ONE (1) STOREY ONE (1) CLASSROOM AND TWO (2) STOREY FOUR (4) CLASSROOM , SIX (6) CLASSROOM AND TEN (10) CLASSROOM SCHOOL BUILDINGS AT DEL GALLEGO AND RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2016₱40.0M
Reported complete (DPWH)
View all 107 projects →

4. Implementation

Contract Amount

₱19,478,543.62

Progress

Reported complete (DPWH)

Start Date

February 16, 2022

Target End

April 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.