Roads17NH0108

ADDITIONAL PAVEMENT WIDTH & LINED CANAL ALONG SDCR, (UNIDOS-TUBO-TUBO SECTION), K1315+000 - K1337+000, UNIDOS-TUBO-TUBO, SURIGAO DEL SUR

ADDITIONAL PAVEMENT WIDTH & LINED CANAL ALONG SDCR, (UNIDOS-TUBO-TUBO SECTION), K1315+000 - K1337+000, UNIDOS-TUBO-TUBO, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 1st DEO, Region XIII. Reported contract value: ₱20,897,809.67. Status: Reported complete (DPWH). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to dpwh.

Surigao del Sur 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱20,897,809.67

Progress

Reported complete (DPWH)

Start Date

January 15, 2018

Target End

June 16, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.