Rehabilitation / Major Repair of Flood Control Structure23FF0044

Rehabilitation of Bicol River Flood Control (Mangayawan Section), Barangay Mangayawan, Canaman, Camarines Sur

Rehabilitation of Bicol River Flood Control (Mangayawan Section), Barangay Mangayawan, Canaman, Camarines Sur is a DPWH-tracked public work in CANAMAN (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱123,941,697.70. Status: Reported complete (DPWH). Contractor on record: 417 LP CONST CORP / STEVEN CONST & SUPPLY. Figures trace to sumbong.

CANAMAN (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure (Along Bicol River), Barangay Taban, Minalabac, Camarines Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0025174

₱1,495,049.00 · FY2023

Released to 0000000 University of - Southeastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱123,941,697.70

Progress

Reported complete (DPWH)

Start Date

May 3, 2023

Target End

February 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.