Roads23MG0044

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-COTABATO-MARBEL RD-K1741+279-K1742+333, SOUTH COTABATO

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-COTABATO-MARBEL RD-K1741+279-K1742+333, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱39,148,202.26. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Kolambog Flood Control/Slope Protection (Sheet Piles) along Cotabato-Marbel Road (Allah River, Kolambog Section), South Cotabato
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-23-0025049

₱1,125,000.00 · FY2023

Released to 0000000 Tawi-Tawi Regional - Agricultural College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱39,148,202.26

Progress

Reported complete (DPWH)

Start Date

May 26, 2023

Target End

September 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.