Roads18AD0108

OFF CARRIAGEWAY IMPROVEMENT TERTIARY ROADS CERVANTES QUIRINO ROAD, K0402+923 - K0403+020, K0405+020 - K0405+260, K0405+660 - K0405+760, K0406+080 - K0406+160, K0406+340 - K0406+907, K0407+108 -K0407+303, K0408+817 - K0408+850, K0409+706 -K0409+794

OFF CARRIAGEWAY IMPROVEMENT TERTIARY ROADS CERVANTES QUIRINO ROAD, K0402+923 - K0403+020, K0405+020 - K0405+260, K0405+660 - K0405+760, K0406+080 - K0406+160, K0406+340 - K0406+907, K0407+108 -K0407+303, K0408+817 - K0408+850, K0409+706 -K0409+794 is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱6,366,431.69. Status: Reported complete (DPWH). Contractor on record: M V SABALBURO CONST AND SUPPLY. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Allangigan 2nd-Oaig Daya-San Nicolas Flood Control (Gabion Revetment Wall) Candon City, Ilocos Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033578

₱0.00 · FY2018

Released to Division of Ilocos Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱6,366,431.69

Progress

Reported complete (DPWH)

Start Date

June 7, 2018

Target End

August 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.