Roads25CJ0194

REHABILITATION OF MAYANTOC ROAD NETWORK (ANNEX 2), MAYANTOC, TARLAC

REHABILITATION OF MAYANTOC ROAD NETWORK (ANNEX 2), MAYANTOC, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: IM CONST CORP. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱75,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Camiling River Cubcub Section, Cubcub, Mayantoc, Tarlac (Package 3)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-25-0005277

₱20,000.00 · FY2025

Released to Tarlac DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱10.7B total · 6 flags

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

April 8, 2025

Target End

September 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.