Flood Control and Drainage24OB0326

CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG (PHASE 7)

CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG (PHASE 7) is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱45,569,750.07. Status: Reported complete (DPWH). Contractor on record: FRANZCOR TRADING. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Drainage System along Westbank Road, Manggahan Floodway, Pasig City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-24-0017712

₱0.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱45,569,750.07

Progress

Reported complete (DPWH)

Start Date

May 3, 2024

Target End

November 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.