Flood Control and Drainage24OB0287

CONSTRUCTION OF FLOOD MITIGATION FACILITY (PUMPING STATION) AT BAGUMBAYAN RIVER, BRGY. BAGUMBAYAN, TAGUIG CITY

CONSTRUCTION OF FLOOD MITIGATION FACILITY (PUMPING STATION) AT BAGUMBAYAN RIVER, BRGY. BAGUMBAYAN, TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱70,918,923.33. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FRANZCOR TRADING. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Facility ( Arkong Bato Relief Pumping Station ) , Brgy. Arkong Bato, Valenzuela City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Metro Manila 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱70,918,923.33

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 1, 2024

Target End

February 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.