Buildings and Facilities23CH0122

PACKAGE 2: IMPROVEMENT/REHABILITATION OF A. FOUR (4) CLASSROOM SCHOOL BUILDING AT ANON ELEMENTARY SCHOOL, FLORIDABLANCA, PAMPANGA B. THREE (3) CLASSROOM SCHOOL BUILDING WITH COMFORT ROOM AT STO. ROSARIO ELEMENTARY SCHOOL, FLORIDABLANCA, PAMPANGA

PACKAGE 2: IMPROVEMENT/REHABILITATION OF A. FOUR (4) CLASSROOM SCHOOL BUILDING AT ANON ELEMENTARY SCHOOL, FLORIDABLANCA, PAMPANGA B. THREE (3) CLASSROOM SCHOOL BUILDING WITH COMFORT ROOM AT STO. ROSARIO ELEMENTARY SCHOOL, FLORIDABLANCA, PAMPANGA is a DPWH-tracked public work in Pampanga 2nd DEO, Region III. Reported contract value: ₱5,340,745.83. Status: Reported complete (DPWH). Contractor on record: M C GERONIMO CONST AND TRADING. Figures trace to dpwh.

Pampanga 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Maintenance of Flood Mitigation Structures along Quitangil River, Magalang, Pampanga - Phase 1
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0019307

₱1,330,761.00 · FY2023

Released to 0000000 Davao Oriental - State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

19 projects · ₱171.2M total · 1 flags

4. Implementation

Contract Amount

₱5,340,745.83

Progress

Reported complete (DPWH)

Start Date

July 8, 2024

Target End

December 4, 2024

5. Audit