Buildings and Facilities19CB0074

CONSTRUCTION OF TWO (2) STOREY EIGHT (8) CLASSROOM AT STO. DOMINGO ES, ORION, BATAAN

CONSTRUCTION OF TWO (2) STOREY EIGHT (8) CLASSROOM AT STO. DOMINGO ES, ORION, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱20,800,000.00. Status: Reported complete (DPWH). Contractor on record: YELLOW GOLD CONST. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-19-0014483

₱60,000.00 · FY2019

Released to Bata National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱20,800,000.00

Progress

Reported complete (DPWH)

Start Date

August 22, 2019

Target End

January 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.