Roads24CC0408

REHABILITATION OF ROADS WITH DRAINAGE CANAL, SANTISSIMA STREET, BAGONG BARRIO, PANDI, BULACAN

REHABILITATION OF ROADS WITH DRAINAGE CANAL, SANTISSIMA STREET, BAGONG BARRIO, PANDI, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱14,849,272.89. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: 3AMR CONST SERVICES INC FORMERLY: 3AMR CONST SERVICES. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Guiguinto Flood Control Structure, Pritil Section, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000335

₱29,019,605.00 · FY2024

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,849,272.89

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 25, 2024

Target End

August 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.