Bridges16FH0005

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, CONSTRUCTION OF PERMANENT BRIDGES, TIBANG BRIDGE ALONG CATANDUANES CIRCUMFERENTIAL ROAD (COMPLETION), SAN ANDRES, CATANDUANES

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, CONSTRUCTION OF PERMANENT BRIDGES, TIBANG BRIDGE ALONG CATANDUANES CIRCUMFERENTIAL ROAD (COMPLETION), SAN ANDRES, CATANDUANES is a DPWH-tracked public work in Catanduanes DEO, Region V. Reported contract value: ₱2,912,146.53. Status: Reported complete (DPWH). Contractor on record: CTC BUILDER AND SUPPLIES INC FOR CTC BU. Figures trace to dpwh.

Catanduanes DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Repair/Improvement of Flood Control and Drainage System along Catanduanes Circumferential Road
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-16-0031332

₱30,063.00 · FY2016

Released to Dingras National High School & Lt. Edgar Foz Me To (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

113 projects · ₱5.1B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION OF NATIONAL ROADS, REHAB./RECONST./UPGRADING OF DAMAGED PAVED NATIONAL ROAD INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4)PRIMARY ROADS DAANG MAHARLIKA (LZ)-K0610+127.70-K0644+136 WIT

Region V, Region V

2017₱144.7M
Reported complete (DPWH)
No sat.

OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-CATANDUANES CIRCUMFERENTIAL ROAD, CATANDUANES

Region V, Region V

2018₱141.4M
Reported complete (DPWH)
No sat.

IMPROVEMENT/WIDENING OF NATIONAL ROADS, WIDENING OF DAANG MAHARLIKA/ASIAN HIGHWAY 26, K0546+740 TO K0552+418.20 WITH EXCEPTIONS, SORSOGON

Region V, Region V

2016₱139.7M
Reported complete (DPWH)
No sat.

STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS, A) PAWA, TABACO CITY, ALBAY; B) SAN PEDRO, IROSIN, SORSOGON; C) BASAG, LIGAO CITY,ALBAY; D) MAURARO, GUINOBATAN, ALBAY

Region V, Region V

2019₱139.0M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT ALONG TIGBAO RIVER, PHASE 2, TACLOBAN CITY

Region VIII, Region VIII

2023₱111.0M
Reported complete (DPWH)

OO2-PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION/IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG CADAC-AN RIVER (UPSTREAM OF TABUC BRID

Region V, Region V

2019₱96.5M
Reported complete (DPWH)
View all 113 projects →

4. Implementation

Contract Amount

₱2,912,146.53

Progress

Reported complete (DPWH)

Start Date

February 25, 2016

Target End

March 26, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.