Construction of Flood Mitigation Structure21I00032

Construction of Storm Surge Protection: Embarkadero Backwater Dike, Right Bank, Barangay Sto. Niño, Tanauan, Leyte

Construction of Storm Surge Protection: Embarkadero Backwater Dike, Right Bank, Barangay Sto. Niño, Tanauan, Leyte is a DPWH-tracked public work in LEYTE, Region VIII. Reported contract value: ₱94,953,700.39. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP. Figures trace to sumbong.

LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Maanda, Leyte, Leyte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱74,106,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010265

₱115,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005378

₱76,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008586

₱50,000,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

107 projects · ₱14.4B total · 65 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF CRUISE PORT AND FACILITIES PACKAGE 3, LEGAZPI CITY, LEGAZPI CITY, ALBAY (2ND LEGISLATIVE DISTRICT

Region V, Region V

2024₱391.8M
Past target date (DPWH On-Going)
No sat.

SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTE

Region VIII, Region VIII

2025₱313.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF COASTAL ROAD, BARANGAY POBLACION, RAPU-RAPU, ALBAY, RAPU-RAPU, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱292.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY MOROCBOROCAN TO BARANGAY POBLACION, R

Region V, Region V

2024₱291.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIP[AG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE I, NAUJAN, ORIENTAL MINDORO

Region IV-B, Region IV-B

2024₱279.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, MAGALLANG-MOROPONROS, LIBON/OAS, ALBAY (PHASE

Region V, Region V

2024₱244.8M
Past target date (DPWH On-Going)
View all 107 projects →

4. Implementation

Contract Amount

₱94,953,700.39

Progress

Reported complete (DPWH)

Start Date

February 22, 2021

Target End

December 31, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.