Flood Control and Drainage25I00125

SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTE

SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱312,976,913.61. Status: Past target date (DPWH On-Going). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25I00125 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · imagery 2021-06-16 → 2025-04-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

107 projects · ₱14.4B total · 65 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF CRUISE PORT AND FACILITIES PACKAGE 3, LEGAZPI CITY, LEGAZPI CITY, ALBAY (2ND LEGISLATIVE DISTRICT

Region V, Region V

2024₱391.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF COASTAL ROAD, BARANGAY POBLACION, RAPU-RAPU, ALBAY, RAPU-RAPU, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱292.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY MOROCBOROCAN TO BARANGAY POBLACION, R

Region V, Region V

2024₱291.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIP[AG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE I, NAUJAN, ORIENTAL MINDORO

Region IV-B, Region IV-B

2024₱279.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, MAGALLANG-MOROPONROS, LIBON/OAS, ALBAY (PHASE

Region V, Region V

2024₱244.8M
Past target date (DPWH On-Going)

Construction of Baao Lakeshore Dike Road (Circumferential Road) in Support of Agriculture and Fishing Industry (Package 3), Baao, Camarines Sur

BAAO (CAMARINES SUR), CAMARINES SUR, Region V

2023₱241.2M
Reported complete (DPWH)
View all 107 projects →

4. Implementation

Contract Amount

₱312,976,913.61

Progress

Past target date (DPWH On-Going)

Start Date

June 13, 2025

Target End

May 8, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Not yet linked to a PSGC area.
Storms whose wind field reached it
Nokaen 2026Koto 2025Kalmaegi 2025Fengshen 2025Bualoi 2025
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.