Typhoon mode · November 23, 2025 – December 3, 2025

Koto (Verbena) 2025

8,051 DPWH flood-control projects worth ₱447.04B sit within 240.8 km of this storm’s track. Peak sustained wind 80 kt (148 km/h, 1-minute average). Being on this list says nothing about a project’s quality. It is where photos after the storm are most useful.

Send a check-in photo

Track and projects

Red line: storm centre (best track). Shaded band: 240.8 km around the track (median 34-kt wind radius near the Philippines, or 100 km where radii were not reported). Blue dots: projects with DPWH coordinates.

Projects in path

8,051

Contract value

₱447.04B

Reported complete

6,642

Ongoing or not reported

1,409

Largest contractors in the path

  1. LEGACY CONST CORP FORMERLY: LEGACY CONST191 · ₱16.54B
  2. QM BUILDERS192 · ₱14.10B
  3. SUNWEST INC FORMERLY: SUNWEST CONST80 · ₱12.62B
  4. EQUI-PARCO CONST CO98 · ₱10.27B
  5. QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST99 · ₱7.44B
  6. IBC INTERNATIONAL BUILDERS CORP78 · ₱7.03B
  7. M MONTESCLAROS ENT INC71 · ₱6.60B
  8. EZJONES CONST INC50 · ₱6.44B
  9. ADFIL CORP57 · ₱5.15B
  10. F GURREA CONST INC67 · ₱4.70B

By DPWH implementing office

  1. Region IV-B161 · ₱34.79B
  2. CEBU339 · ₱22.43B
  3. Region VIII150 · ₱19.10B
  4. Region X181 · ₱17.93B
  5. LEYTE234 · ₱13.04B
  6. MISAMIS ORIENTAL141 · ₱11.25B
  7. Cebu 7th DEO143 · ₱11.07B
  8. Region VII88 · ₱11.06B
  9. Region XIII71 · ₱10.76B
  10. Region VI86 · ₱9.71B
  11. Romblon DEO118 · ₱7.29B
  12. BUKIDNON90 · ₱6.97B

Satellite before and after

Largest projects in the path with archived imagery. Imagery dates are before and after the contract, not the storm. They are not proof of completion.

Imagery © Esri, Maxar, Earthstar Geographics, and the GIS User Community (World Imagery Wayback).

Projects to check (largest 1,500 of 8,051)

Near one of these? Open the project and use “Check in” to add a dated photo. Faces and plates are blurred automatically.

ProjectPlaceCostStatusContractorkm from track
DESIGN AND BUILD OF COASTAL DIKE AND DRAINAGE IMPROVEMENT, CATBALOGAN CITY, SAMARFlood Control Management Cluster₱744.4M87% reported progressHI-TONE CONST & DEVELOPMENT CORP FORMERLY205Check in
METRO CEBU FLOOD CONTROL PROJECT AND DRAINAGE IMPROVEMENT PROJECT - SUBANG DAKU, LAHUG, GUADALUPE, KINALUMSAN, TIPOLO, TEJERO AND BULACAO RIVER BASINS, CEBU CITYFlood Control Management Cluster₱684.0M91% reported progressARN BUILDERS INC FOR: ARN BUILDERS13Check in
METRO CEBU FLOOD CONTROL PROJECT - FLOOD CONTROL AND DRAINAGE IMPROVEMENT PROJECT, KINALUMSAN RIVER, DULJO, LABANGON AND MAMBALING, CEBU CITYFlood Control Management Cluster₱553.8M22% reported progressRAYMAN BUILDERS INC21Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LAKE MAINIT - TUBAY RIVER (KALINAWAN - KARAK-AN SECTION), TUBAY, AGUSAN DEL NORTERegion XIII₱465.1MReported completeEQUI-PARCO CONST CO23Check in
CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY, DRAINAGE SYSTEM, CATBALOGAN CITY, INCLUDING ANTIAO RIVER CONTROL, SAMAR PROVINCEFlood Control Management Cluster₱445.3MReported completeMSB VITUG CONST204Check in
CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY DRAINAGE SYSTEM, CATBALOGAN CITY INCLUDING ANTIAO RIVER CONTROL, SAMARFlood Control Management Cluster₱438.8MReported completeMSB VITUG CONST205Check in
FLOOD RISK MANGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR), JICA LOAN NO. PH-P259, CONTRACT PACKAGE 1 (BONBON-KAUSWAGAN)Flood Control Management Cluster₱371.1M86% reported progressA M ORETA & CO INC 108145Check in
CONSTRUCTION OF FLOOD CONTROL ALONG SIBALOM RIVER, SIBALOM. ANTIQUERegion VI₱358.0M47% reported progressMAC BUILDERS CORP FORMERLY: MAC BUILDERS DEVELOPMENT CORP26Check in
SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14B, TACLOBAN CITY, LEYTERegion VIII₱313.0M0% reported progressL N R CONST151Check in
SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTERegion VIII₱313.0M0% reported progressSUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP151Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLONRegion IV-B₱297.0M90% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST207Check in
1. CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BURABUD-AN, ABUYOG, LEYTE; 2. CONSTRUCTION OF FLOOD CONTROL STRUCTURE CADAC-AN RIVER, BARANGAY PAGSANG-AN, ABUYOG, LEYTERegion VIII₱294.9MReported completeJUCONS CONST OPC FORMERLY:JUCONS CONST &SUPPLY94Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE MUMPONG RIVER, TUBAN-BATONG BUHAY, BRGY. TUBAN, SABLAYAN, OCC. MINDORORegion IV-B₱291.8M38% reported progressSUNWEST INC FORMERLY: SUNWEST CONST174Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, MUMPONG RIVER, TUBAN-STA. LUCIA, BRGY. TUBAN, SABLAYAN, OCC. MINDORORegion IV-B₱291.5M37% reported progressSUNWEST INC FORMERLY: SUNWEST CONST174Check in
CONSTRUCTION/ IMPROVEMENT OF FLOOD MITIGATION STRUCTURES WITH RECHANNELIZATION ALONG ANDANAN RIVER BANK (DOWNSTREAM), BAYUGAN CITY, AGUSAN DEL SURRegion XIII₱289.5MReported completeADFIL CORP72Check in
CONSTRUCTION/DESILTATION MAON CATCHMENT AREA - VILLAKANANGA CREEK - CALOT - BONBON CREEK, BUTUAN CITYRegion XIII₱289.5MReported completeEQUI-PARCO CONST CO60Check in
CLUSTER 5 - 5.1: CONSTRUCTION OF BUTUAN CITY REVETMENT ALONG AGUSAN RIVER, URDUJA SECTION PACKAGE 1, BUTUAN CITY 5.2: CONSTRUCTION OF BUTUAN CITY REVETMENT ALONG AGUSAN RIVER, URDUJA SECTION PACKAGE 2, BUTUAN CITYRegion XIII₱289.5MReported completeEQUI-PARCO CONST CO57Check in
SUSTAINABLE INFRASTRUCTURE PROECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CARMEN PORT, SAN AGUSTIN, ROMBLONRegion IV-B₱289.5MReported completeLEGACY CONST CORP FORMERLY: LEGACY CONST223Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLONRegion IV-B₱289.5M57% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST158Check in
Construction of Dubduban Flood Control Structure, San Agustin, Tablas Island RomblonALCANTARA (ROMBLON), ROMBLON₱289.5MReported completeLEGACY CONST CORP FORMERLY: LEGACY CONST218Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MONGPONG, BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORORegion IV-B₱289.5MReported completeLEGACY CONST CORP FORMERLY: LEGACY CONST167Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD AND CAUSEWAY FOR TOURISM ALONG AZAGRA PORT, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLONRegion IV-B₱289.5MReported completeST TIMOTHY CONST CORP197Check in
Construction of Flood Control Structure (River Training Works) along Mompong River (Downstream), Sablayan, Occidental MindoroSABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱289.5MReported completeGREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC168Check in
CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1Region IV-B₱289.5M62% reported progressST TIMOTHY CONST CORP227Check in
Construction of Road Dike/Esplanade along Pangalaan River (Left Side), Naujan, Oriental MindoroNAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO₱289.5MReported completeALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP235Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CAJIDIOCAN PORT, SIBUYAN ISLAND, ROMBLONRegion IV-B₱289.5MReported completeST TIMOTHY CONST CORP207Check in
Construction of Road Dike/Esplanade along Sitio Anduyanan, Paluan, Occidental MindoroPALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱289.5MReported completeAMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP211Check in
Construction of Paluan Shore Protection and Causeway Development, Sitio Ipol Section, Occidental MindoroPALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱289.5MReported completeD T RECIO INC209Check in
SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY FOR TOURISM ALONG AMBULONG PORT, MAGDIWANG, SIBUYAN ISLAND, ROMBLONRegion IV-B₱289.5MReported completeST PIUS CONST AND SUPPLY219Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG POBLACION SAN FERNANDO, SIBUYAN ISLAND, ROMBLONRegion IV-B₱289.5MReported completeST TIMOTHY CONST CORP199Check in
Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, RomblonSAN ANDRES (ROMBLON), ROMBLON₱289.5MReported completeYPR GEN CONTRACTOR AND CONST SUPPLY INC209Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SABLAYAN PORT, ROMBLON, ROMBLONRegion IV-B₱289.5MReported completeST PIUS CONST AND SUPPLY215Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PHASE I, NAUJAN, OR. MINDORORegion IV-B₱287.2M86% reported progressSUNWEST INC FORMERLY: SUNWEST CONST228Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. VICTORIA SECTION, PHASE III, SABLAYAN, OCC. MINDORORegion IV-B₱287.1M85% reported progressSUNWEST INC FORMERLY: SUNWEST CONST183Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ODIONGAN RIVER, PACKAGE 3, GINGOOG CITY, MISAMIS ORIENTALRegion X₱286.3MReported completeVICENTE T LAO CONST87Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE-LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE 1 & 2, URBAN DRAINAGE SYSTEM IN BUTUAN CITY (MANDACPAN-BONBON CHANNEL IMPROVEMENT, DOWNSTREAM), PACKAGE 3, BUTUAN CITYRegion XIII₱285.7M70% reported progressEQUI-PARCO CONST CO60Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE-LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE 1 & 2, URBAN DRAINAGE SYSTEM IN BUTUAN CITY (MANDACPAN-BONBON CHANNEL IMPROVEMENT, DOWNSTREAM), PACKAGE 4, BUTUAN CITYRegion XIII₱285.7M70% reported progressEQUI-PARCO CONST CO60Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG RIVER, SITIO KULI-KULI SECTION (RS), ARMADO, STA. 000+234-STA. 000+900, ABRA DE ILRegion IV-B₱284.3M30% reported progressD T RECIO INC209Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. CENTRAL-BRGY. SAN AGUSTIN, STA. 000+240-STA. 000+735.5 (LEFT SIDE), SAN JOSE, OCC. MINDRegion IV-B₱284.2M65% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST167Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. BATASAN, STA. 000+000-STA. 000+473.35, SAN JOSE, OCC. MINDORORegion IV-B₱284.2M65% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST173Check in
Construction of Flood Control Structure at Tagoloan River, Package 6, Misamis OrientalTAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL₱282.3MReported completeRAMISES CONST / EQUI-PARCO CONST CO136Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 9, MISAMIS ORIENTALRegion X₱282.2MReported completeME 3 CONST136Check in
Construction of Flood Control Structure at Tagoloan River, Package 8, Misamis OrientalTAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL₱280.8MReported completeEQUI-PARCO CONST CO / TRIPARCO DEVELOPMENT CORP136Check in
SUSTAINABLE INFRASTRUCTURE POJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG UBI RIVER, BRGY. TAGUMPAY, PHASE V, NAUJAN, OR. MINDORORegion IV-B₱280.2M91% reported progressSUNWEST INC FORMERLY: SUNWEST CONST230Check in
SUISTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. VICTORIA SECTION, PHASE I, SABLAYAN, OCC. MINDORORegion IV-B₱280.2M84% reported progressSUNWEST INC FORMERLY: SUNWEST CONST184Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG DULANGAN RIVER, BRGY. EVANGELISTA, PHASE I, NAUJAN, ORIENTAL MINDORORegion IV-B₱280.1M78% reported progressSUNWEST INC FORMERLY: SUNWEST CONST234Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING M,AJOR/STRATEGIC PUBLIC BUILDINGS/FCILITIES- CONST. OF ROAD DIKE ALONG M,AG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PHASE III, NAUJAN, ORIENTAL MINDORORegion IV-B₱280.1M89% reported progressSUNWEST INC FORMERLY: SUNWEST CONST230Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILUITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE IV, NAUJAN, OR. MINDORORegion IV-B₱279.9M86% reported progressSUNWEST INC FORMERLY: SUNWEST CONST232Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PJHASE IV, NAUJAN, ORIENTAL MINDORORegion IV-B₱279.9M88% reported progressSUNWEST INC FORMERLY: SUNWEST CONST230Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD DIKE ALONG PATRICK RIVER, BRGY. TAGUMPAY SECTION, PHASE II, SABLAYAN, OCC. MINDORORegion IV-B₱279.7M92% reported progressSUNWEST INC FORMERLY: SUNWEST CONST183Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PHASE II, NAUJAN, OR. MINDORORegion IV-B₱279.7M87% reported progressSUNWEST INC FORMERLY: SUNWEST CONST229Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. VICTORIA SECTION, PHASE II, SABLAYAN, OCC. MINDORORegion IV-B₱279.6M86% reported progressSUNWEST INC FORMERLY: SUNWEST CONST183Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY.INARAWAN, PHASE II, NAUJAN, OR. MINORTORegion IV-B₱279.4M78% reported progressSUNWEST INC FORMERLY: SUNWEST CONST231Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROADS/BOULEVARD & CAUSEWAY FOR TOURISM ALONG STA. FE PORT, TABLAS ISLAND, ROMBLONRegion IV-B₱279.4M89% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST170Check in
Construction of Flood Control Structure at Tagoloan River, Package 7, Misamis OrientalTAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL₱279.4MReported completeEQUI-PARCO CONST CO / TRIPARCO DEVELOPMENT CORP136Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIP[AG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE I, NAUJAN, ORIENTAL MINDORORegion IV-B₱279.4M82% reported progressSUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP231Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE III, NAUJAN, OR. MINDORORegion IV-B₱279.2M78% reported progressSUNWEST INC FORMERLY: SUNWEST CONST232Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. TAGUMPAY SECTION, PHASE I, SABLAYAN, OCC. MINDORORegion IV-B₱278.8M94% reported progressSUNWEST INC FORMERLY: SUNWEST CONST183Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PATRICK RIVER, SITIO MANAMOK, BRGY. TAGUMPAY, SABLAYAN, OCC. MINDORORegion IV-B₱277.8M37% reported progressSUNWEST INC FORMERLY: SUNWEST CONST183Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PATRICK RIVER, OLD TAGUMPAY, BRGY. TAGUMPAY, SABLAYAN, OCC. MINDORORegion IV-B₱277.5M37% reported progressSUNWEST INC FORMERLY: SUNWEST CONST183Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (UPSTREAM), SAN JOSE, OCC. MINDORORegion IV-B₱276.6M61% reported progressD T RECIO INC160Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (DOWNSTREAM), SAN JOSE, OCC. MINDORORegion IV-B₱276.4M59% reported progressD T RECIO INC160Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG PANGALAAN RIVER, (LEFT SIDE), BRGY. SAMPAGUITA, NAUJAN, OR. MINDORORegion IV-B₱276.2M24% reported progressLE BRON CONST238Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (DOWNSTREAM LS), PACKAGE C, NAUJAN, OR. MINDORORegion IV-B₱276.1M30% reported progressANORE CONST239Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, (UPSTREAM), BRGY. MULAWIN-BRGY. DEL PILAR, NAUJAN,Region IV-B₱276.0M32% reported progressHGG BUILDERS234Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (LS), PACKAGE B, NAUJAN, OR. MINDORORegion IV-B₱276.0M24% reported progressANORE CONST239Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. APITONG SECTION (DOWNSTREAM LS), NAUJAN, OR. MINDORORegion IV-B₱275.8M61% reported progressRAYMAN BUILDERS INC233Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. ADELA (DOWNSTREAM), RIZAL, OCC.MINDORORegion IV-B₱275.8M60% reported progressD T RECIO INC158Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DFIKE, PANGALAAN RIVER, DOWNSTREAM (RIGHT SIDE), PACKAGE A, NAUJAN, OR. MINDORORegion IV-B₱275.7M79% reported progressRAYMAN BUILDERS INC240Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. APITONG SECTION (UPSTREAM LS), NAUJAN, OR. MINDORORegion IV-B₱275.6M60% reported progressRAYMAN BUILDERS INC232Check in
REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITYRegion VIII₱274.3M65% reported progressE M CUERPO INC118Check in
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PUGAAN RIVER, PACKAGE 5, MISAMIS ORIENTALRegion X₱274.2M73% reported progressEQUI-PARCO CONST CO135Check in
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PUGAAN RIVER, PACKAGE 6, MISAMIS ORIENTALRegion X₱274.2M60% reported progressEQUI-PARCO CONST CO135Check in
OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (UPSTREAM), LILOAN, CEBURegion VII₱269.2M69% reported progressBNR CONST & DEVELOPMENT CORP36Check in
CONSTRUCTION/ REHABILITATION OF CAGAYAN DE ORO RIVER BASINS, CALA-CALA SECTION, BRGY. MACASANDIG, CAGAYAN DE ORO CITYRegion X₱268.0MReported completeADFIL CORP151Check in
CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL STRUCTURES IN METRO CEBU, BRGY. PASIL AND ERMITA, BRGY. TEJERO AND BRGY. TIPOLO, CEBU CITYFlood Control Management Cluster₱266.6MReported completeMSB VITUG CONST17Check in
Construction of Flood Control Structure at Tagoloan River, Package 10, Misamis OrientalTAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL₱266.2MReported completeHAPPY ALL3 BUILDERS CORP / EQUI-PARCO CONST CO136Check in
CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 4+780.00 - STATION 5+480, SECTION 5 PHASE 11, BRGY. STA. CRUZ, TANAUAN, LEYTERegion VIII₱265.3MReported completeSUNWEST INC FORMERLY: SUNWEST CONST140Check in
CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 1+900 - STATION 2+550, SECTION 5 PHASE 9, BRGY. SAN JOAQUIN, PALO, LEYTERegion VIII₱263.4MReported completeWTG CONST141Check in
WIDENING OF BRIDGE - SIBALOM BR. (B00123PN) ALONG ILOILO - ANTIQUE RDRegion VI₱259.4MReported completeADVANCED FOUNDATION CONST SYSTEMS CORP17Check in
CONSTRUCTION OF LOWER AGUSAN RIVER BANK PROTECTION, AGAO - URDUJA - PPA SECTION, BUTUAN CITY, AGUSAN DEL NORTERegion XIII₱250.9MReported completeEQUI-PARCO CONST CO57Check in
REPAIR / REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS AND BRIDGES, FLOOD CONTROL, OTHER PUBLICCebu 7th DEO₱250.9MReported completeQM BUILDERS54Check in
Construction of Road Dike along Bucayao River (East Side), Sitio Malaya Section, Barangay Tagumpay, Naujan, Oriental MindoroNAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO₱247.5MReported completeST TIMOTHY CONST CORP228Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLONRegion IV-B₱247.5M93% reported progressYPR GEN CONTRACTOR AND CONST SUPPLY INC187Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAYRegion IV-B₱247.5M94% reported progressYPR GEN CONTRACTOR AND CONST SUPPLY INC187Check in
Construction of Road Dike along Bucayao River (East Side), Sitio Malinao Section, Barangay Tagumpay, Naujan, Oriental MindoroNAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO₱247.5MReported completeELITE GEN CONTRACTOR AND DEVELOPMENT CORP227Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF LIGAYA-STA. LUCIA COASTAL ROAD (STA. LUCIA SECTION), SABLAYAN, OCC. MINDORORegion IV-B₱247.5M79% reported progressANORE CONST165Check in
Construction of Road Dike aling Mag-asawang Tubig River, Sampaloc Section, Barangay Sto. Niño, Naujan, Oriental MindoroNAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO₱247.5MReported completeRAYMAN BUILDERS INC237Check in
Construction of Road Dike along Mag-asawang Tubig River, Dayapan Section, Barangay Sto. Niño, Naujan, Oriental MindoroNAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO₱247.5MReported completeRAYMAN BUILDERS INC236Check in
OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST OF LOBOC RIVER CONTROL STRUCTURE, UGPONG SECTION TO VILLAFLOR SECTION, LEFT SIRegion VII₱241.2M83% reported progressSUPREME ABF CONST49Check in
OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION SAWANG, RIGHT SIDE PHASE 1, LOBOC,Region VII₱241.2M80% reported progressHGG BUILDERS48Check in
OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION ONDOL, RIGHT SIDE, LOBOC, BOHOLRegion VII₱241.2M78% reported progressHGG BUILDERS & SUPPLY49Check in
CONSTRUCTION OF JALIOBONG-SAN ISIDRO RIVER CONTROL PROJECT, KITCHARAO, AGUSAN DEL NORTERegion XIII₱241.2MReported completeADFIL CORP12Check in
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (MAHAY - VIADUCT SECT), BUTUAN CITY, AGUSAN DEL NORTERegion XIII₱241.2MReported completeTRIPARCO DEVELOPMENT CORP57Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF TUGDAN CAUSEWAY, ALCANTARA, TABLAS ISLAND, ROMBLONRegion IV-B₱241.2MReported completeLEGACY CONST CORP FORMERLY: LEGACY CONST190Check in
CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES AND CHANNELIZATION, FATIMA, DULAG, LEYTE 2ND LD, DULAG, LEYTERegion VIII₱241.2MReported completeEZJONES CONST INC120Check in
FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURES ALONG BALETE RIVER, PHASE 2, BRGY. PAPANDUNGIN, GLORIA, OR. MINDORORegion IV-B₱241.2M71% reported progressEIGHT J'S CONST SERVICES233Check in
SUSTAINABLE INFRASTCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLI BUILDINGS/FACILITIES- CONST. OF TABLAS EAST COAST BOULEVARD, SANTA MARIA, TABLAS ISLAND, ROMBLONRegion IV-B₱241.2MReported completeLEGACY CONST CORP FORMERLY: LEGACY CONST198Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, PHASE 1, BRGY. PAPANDUNGIN, GLORIA, OR. MINDORORegion IV-B₱241.2M76% reported progressNEW RICH GEN CONTRACTOR SERVICES & TRADING CO INC233Check in
FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER, BRGY. MAOYON (LS), PTO. PRINCESA CITY, PALAWANRegion IV-B₱241.2M94% reported progressMAMSAR CONST AND INDUSTRIAL CORP194Check in
FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, BRGY. BALETE, GLORIA, OR. MINDORIORegion IV-B₱241.2M82% reported progressEIGHT J'S CONST SERVICES233Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, BRGY. BALETE - BRGY. PAPANDUNGIN, GLORIA, ORIENTAL MINDORORegion IV-B₱241.2M81% reported progressEIGHT J'S CONST SERVICES233Check in
Construction of Flood Control Structure along Abra de Ilog River, Sitio Kuli-Kuli Section, Armado, Abra de Ilog, Occidental MindoroABRA DE ILOG (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱241.2MReported completeGOLDEN J'S CONST SERVICES209Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 1, BRGY. SAN VICENTE, SANTA CRUZ, OCRegion IV-B₱241.2MReported completeSILVERWOLVES CONST CORP203Check in
Construction of Road Dike/Esplanade along Pangalaan River (Right Side), Naujan, Oriental MindoroNAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO₱241.2MReported completeGREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC238Check in
Construction of Road Dike/Esplanade along Sitio Katanlawan, Paluan, Occidental MindoroPALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱241.2MReported completeALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP210Check in
FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENAMNCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER (RS), STA. 000+000-STA. 000+623.17, PTO. PRINCESA CITY, PALAWANRegion IV-B₱241.2M96% reported progressMAMSAR CONST AND INDUSTRIAL CORP195Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 2, BRGY. SAN VICENTE, SANTA CRUZ, OCRegion IV-B₱241.2MReported completeSILVERWOLVES CONST CORP202Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURE PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIVER CONTROL STRUCTURE ALONG MAYHA-TULAY RIVER, ODIONGAN, ROMBLONRegion IV-B₱241.2M83% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST192Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. CARMEN SECTION, SAN AGUSTIN, TABLAS ISLAND, ROMBLONRegion IV-B₱241.2M87% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST223Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF COASTAL ROAD, PHASE 2, STA. FE, TABLAS ISLAND, ROMBLONRegion IV-B₱241.2M93% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST169Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG RIVER, PERLAS SECTION, WAWA, ABRA DE ILOG, OCC. MINDORORegion IV-B₱241.2M83% reported progressST TIMOTHY CONST CORP229Check in
Construction of Paluan Shore Protection and Causeway Development, Sitio Malugao Section, Occidental MindoroPALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱241.2MReported completeD T RECIO INC209Check in
FLOOD MANAGEMENT PROGRAM- CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF DUBDUBAN FLOOD CONTROL STRUCTURE (DOWNSTREAM), SAN AGUSTIN, TABLAS ISLAND, ROMBLONRegion IV-B₱241.2M82% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST218Check in
FLOOD MANAGEMENT PROGRAM- CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF DUBDUBAN FLOOD CONTROL STRUCTURE (UPSTREAM), SAN AGUSTIN, TABLAS ISLAND, ROMBLONRegion IV-B₱241.2M87% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST217Check in
Construction of Flood Control Structure along Abra de Ilog River, Cabacao Section, Abra de Ilog, Occidental MindoroABRA DE ILOG (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱241.2MReported completeGOLDEN J'S CONST SERVICES213Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 1, BRGY. MULAWIN, NAUJAN, OR. MINDORORegion IV-B₱239.3M35% reported progressHGG BUILDERS233Check in
CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 2+550 - STATION 3+180, SECTION 5 PHASE 10, BRGY. SAN JOAQUIN, PALO, LEYTERegion VIII₱239.0MReported completeSUNWEST INC FORMERLY: SUNWEST CONST141Check in
CONSTRUCTION OF RIVER FLOOD MITIGATION STRUCTURE ALONG HANAGDONG BRIDGE, SURIGAO-AGUSAN WEST COASTAL ROAD, SURIGAO DEL NORTERegion XIII₱238.8M46% reported progressTRIPARCO DEVELOPMENT CORP1Check in
CONSTRUCTION OF LINONGGANAN RIVER FLOOD CONTROL ALONG SURIGAO-AGUSAN WEST COASTAL ROAD, BRGY. LINONGGANAN, SAN FRANCISCO, SURIGAO DEL NORTERegion XIII₱238.6M19% reported progressTRIPARCO DEVELOPMENT CORP11Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ILVITA RIVERBANK PROTECTION WORKS ALONG AMNAY RIVER (DOWNSTREAM), SABLAYAN, OCC. MINDORORegion IV-B₱238.3M80% reported progressANORE CONST186Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 11, MISAMIS ORIENTALRegion X₱237.6M61% reported progressRAMISES CONST136Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 13, MISAMIS ORIENTALRegion X₱237.6M61% reported progressTRIPARCO DEVELOPMENT CORP136Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 14, MISAMIS ORIENTALRegion X₱237.6M61% reported progressEQUI-PARCO CONST CO136Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 12, MISAMIS ORIENTALRegion X₱237.6M65% reported progressEQUI-PARCO CONST CO136Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, BRGY. CANUBING II (DOWNSTREAM), STA. 000+320-STA. 000+613.90, CALAPAN, OR. MINDORORegion IV-B₱237.0M52% reported progressADSL CONST & TRADING236Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADFE ALONG PATRICK RIVER (UPSTREAM), BRGY. SAN FRANCISCO-BRGY. PAETAN SECTION, STA. 000+668.34-STA. 001+000 (Region IV-B₱236.9M9% reported progressSILVERWOLVES CONST CORP187Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, BRGY. CANUBING II, STA. 000+000-STA. 000+305.50, CALAPAN, OR. MINDORORegion IV-B₱236.9M38% reported progressADSL CONST & TRADING236Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG PATRICK RIVER (UPSTREAM), BRGY. PAETAN-BRGY. TAGUMPAY, STA.01+010-STA. 001+335.99 (LEFT SIDE), SABRegion IV-B₱236.9M64% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST187Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIVERBANK PROTECTION WORKS ALONG LABANGAN RIVER (UPSTREAM), BRGY. MURTHA, STA. 000+000-STA. 000+465.82, SAN JOSE, OCC. MINDORRegion IV-B₱236.9M71% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST168Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC B UILDINGS/FACILITIES- CONST. OF RIVERBANK PROTECTION WORKS ALONG LABANGAN RIVER (DOWNSTREAM), BRGY. MURTHA, STA. 000+480-STA. 000+921.80, SAN JOSE, OCC. MINRegion IV-B₱236.9M71% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST168Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG PATRICK RIVER (DOWNSTREAM), BRGY. PAETAN-BRG. TAGUMPAY, STA. 001+345-STA. 001+639.06 (LEFT SIDE), SRegion IV-B₱236.9M62% reported progressLEGACY CONST CORP FORMERLY: LEGACY CONST187Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. AMBULONG SECTION, MAGDIWANG, SIBUYAN ISLAND, ROMBLONRegion IV-B₱236.4MReported completeYPR GEN CONTRACTOR AND CONST SUPPLY INC219Check in
OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, TAMBANGAN SECTION (LEFT SIDE), LOAY, BOHOLRegion VII₱236.4M0% reported progressSUPREME ABF CONST & CONST SUPPLY CO INC51Check in
OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, TAMBANGAN SECTION (RIGHT SIDE), LOAY, BOHOLRegion VII₱236.3M0% reported progressSUPREME ABF CONST51Check in
CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM ALONG BANGON RIVER, PHASE 3, BARANGAY SAN JOSE, PALO, LEYTERegion VIII₱236.2M20% reported progressEZJONES CONST INC143Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM), PHASE 2, TACLOBAN CITYRegion VIII₱236.1M31% reported progressEZJONES CONST INC158Check in
BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE, BALETE RIVER, BRGY. PAPANDUNGIN, GLORIA, OR. MINDORORegion IV-B₱236.1M71% reported progressALRIE CONST SERVICES232Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 2, BRGY. SAN LUIS, NAUJAN, OR. MINDORRegion IV-B₱234.3M87% reported progressGREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC232Check in
CLUSTER 1: 1. CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE A). SITIO BAGANG, BRGY. CABACUNGAN, DULAG, LEYTE 2. CONSTRUCTION (EXTENSION) OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE A), BRGY. FATIMA, DULAG, LEYTERegion VIII₱233.5MReported completeEZJONES CONST INC120Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD DIKE/ESPLANADE ALONG BUSUANGA RIVER, BRGY. AGUAS, RIZAL, OCC. MINDORegion IV-B₱232.8M88% reported progressSUNWEST INC FORMERLY: SUNWEST CONST173Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG BUSUANGA RIVER, BRGY. PITOGO, RIZAL, OCC. MINDORRegion IV-B₱232.8M82% reported progressSUNWEST INC FORMERLY: SUNWEST CONST172Check in
FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG, SITIO KALINYAWAN SECTION, SAN VICENTE, ABRA DE ILOG, OCC. MINDORORegion IV-B₱232.6M72% reported progressANORE CONST219Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OCRegion IV-B₱232.4M90% reported progressELITE GEN CONTRACTOR AND DEVELOPMENT CORP160Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE I, BRGY. SAN LUIS, NAUJAN, OR. MINDORRegion IV-B₱232.4M82% reported progressNEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST232Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. ADELA, SAN JOSE, OCC. MINDORORegion IV-B₱232.4M85% reported progressYPR GEN CONTRACTOR AND CONST SUPPLY INC158Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BONGABONG RIVER, BRGY. LISAP-BRGY. BATANGAN (UPSTREAM), STA. 000+330-STA. 000+649.50, BONGABONG, OR. MINDORRegion IV-B₱231.5M28% reported progressJJPR CONST SERVICES204Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURES, MOMPONG RIVER, BRGY. SANTA LUCIA (UPSTREAM-RS), SABLAYAN, OCC. MINDORORegion IV-B₱231.3M30% reported progressANORE CONST169Check in
CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (UPSTREAM-LS), GLORIA, OR. MINDORORegion IV-B₱231.2M0% reported progressGOLDEN J'S CONST SERVICES232Check in
FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BONGABONG RIVER, BRGY. LISAP-BRGY. BATANGAN (DOWNSTREAM), STA. 000+680-STA. 000+995.85, BONGABONG, O.Region IV-B₱231.1M45% reported progressJIIK CONST SERVICES204Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE WITH ESPLANADE ALONG POLA RIVER, BRGY. LUMANGBAYAN SECTION (UPSTREAM/LS), STA. CRUZ, OCC. MINDORORegion IV-B₱231.1M60% reported progressD T RECIO INC192Check in
CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (DOWNSTREAM-LS), GLORIA, OR. MINDORORegion IV-B₱231.0M0% reported progressGOLDEN J'S CONST SERVICES232Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE WITH ESPLANADE ALONG POLA RIVER, BRGY. LUMANGBAYAN SECTION (DOWNSTREAM/LS), STA. CRUZ, OCC. MINDORORegion IV-B₱231.0M60% reported progressD T RECIO INC191Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, MOMPONG RIVER,BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORORegion IV-B₱230.2M61% reported progressANORE CONST168Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BANSUD RIVER, BRGY. CONRAZON, BANSUD, OR. MINDORORegion IV-B₱230.1M59% reported progressLE BRON CONST223Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, (UPSTREAM, RIGHT SIDE), BRGY. BALETE, GLORIA, OR. MINDORORegion IV-B₱230.1M46% reported progressALRIE CONST SERVICES234Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF RIVERSIDE PROTECTION STRUCTURE, PILI RIVER, UPSTREAM, POBLACION, SAN FERNANDO, SIBUYAN ISLAND, ROMBLONRegion IV-B₱230.1M90% reported progressYPR GEN CONTRACTOR AND CONST SUPPLY INC200Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER DOWNSTREAM, GLORIA, OR. MINDORORegion IV-B₱230.1M78% reported progressJIIK CONST SERVICES233Check in
CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG PALUAN RIVER, BRGY. SAN JOSE POBLACION (BRGY. 6) SECTION (L/S), PALUAN, OCC. MINDORORegion IV-B₱230.1M43% reported progressANORE CONST209Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG PANGALAAN RIVER, BRGY. SAMPAGUITA, PHASE 2, NAUJAN, OR. MINDORORegion IV-B₱230.0M25% reported progressLE BRON CONST239Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, (DOWNSTREAM, RIGHT SIDE), BRGY. BALETE, GLORIA, OR. MINDORORegion IV-B₱230.0M43% reported progressJIIK CONST SERVICES234Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, (UPSTREAM, LEFT SIDE), BRGY. BALETE, GLORIA, OR. MINDORORegion IV-B₱230.0M45% reported progressALRIE CONST SERVICES234Check in
CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG PALUAN RIVER, BRGY. SAN JOSE POBLACION (BRGY. 6) SECTION (R/S), PALUAN, OCC. MINDORORegion IV-B₱230.0M42% reported progressANORE CONST209Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BANSUD RIVER BRGY. CONRAZON (UPSTREAM), BANSUD, OR. MINDORORegion IV-B₱230.0M61% reported progressLE BRON CONST223Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, (DOWNSTREAM), BRGY. MULAWIN-BRGY. DEL PILAR, NAUJAN, OR. MINDORORegion IV-B₱230.0M34% reported progressHGG BUILDERS234Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BONGABONG RIVER, BONGABONG, OR. MINDORORegion IV-B₱229.9M42% reported progressJJPR CONST SERVICES204Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN-BRGY. SAMPAGUITA (UPSTREAM), PACKAGE A, NAUJAN, OR. MINDORORegion IV-B₱229.9M70% reported progressRAYMAN BUILDERS INC240Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN-BRGY. SAMPAGUITA, PACKAGE B, NAUJAN, OR. MINDORORegion IV-B₱229.9M25% reported progressRAYMAN BUILDERS INC241Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BONGABONG RIVER UPSTREAM, BONGABONG, OR. MINDORORegion IV-B₱229.8M32% reported progressJJPR CONST SERVICES204Check in
FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF RIVERSIDE PROTECTION STRUCTURE, DOWNSTREAM, BRGY. PUNONG, SAN FERNANDO, ROMBLONRegion IV-B₱229.8M88% reported progressYPR GEN CONTRACTOR AND CONST SUPPLY INC206Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. SAMPAGUITA (DOWNSTREAM), NAUJAN, OR. MINDORORegion IV-B₱229.6M60% reported progressRAYMAN BUILDERS INC239Check in
Construction of Basey Tide Embankment, Basey, SamarSAMAR (WESTERN SAMAR)₱227.8MReported completeNORTHERN BUILDERS / RIANNE CONST158Check in
Construction of Basey Tide Embankment, Basey, SamarSAMAR (WESTERN SAMAR)₱227.8MReported completeNORTHERN BUILDERS / RIANNE CONST158Check in
Construction of Basey Tide Embankment, Basey, SamarSAMAR (WESTERN SAMAR)₱227.8MReported completeNORTHERN BUILDERS / RIANNE CONST158Check in
CLUSTER 3: 1. CONSTRUCTION OF STORM SURGE PROTECTION: TIDE EMBANKMENT, SUBSECTION 6.8, BARANGAY SAN ROQUE, TANAUAN, LEYTE; 2. CONSTRUCTION OF STORM SURGE PROTECTION: TIDE EMBANKMENT, SUBSECTION 6.9, BARANGAY SAN ROQUE, TANAUAN, LEYTERegion VIII₱226.2MReported completeEZJONES CONST INC138Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF BANK PROTECTION STRUCTURE WITH ROAD DIKE ALONG LUMINTAO RIVER, BRGY. MAGSIKAP AND BRGY. MALAWAAN (DOWNSTREAM), RIZAL, OCC. MINDORORegion IV-B₱225.6M85% reported progressAMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP163Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROXAS BY-PASS ROAD, ROXAS, OR. MINDORORegion IV-B₱221.9M86% reported progressGREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC198Check in
CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF BANK PROTECTION STRUCTURE WITH ROAD DIKE ALONG LUMINTAO RIVER, BRGY. MAGSIKAP (UPSTREAM), RIZAL, OCC. MINDORORegion IV-B₱221.9M64% reported progressD T RECIO INC163Check in
Construction of Road Dike/Esplanade along Patrick River, Sablayan, Occidental MindoroSABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO₱217.1MReported completeSUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP184Check in
OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONSTN/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURURE, GOTOZAN SECTION, LOBOC, BOHOLRegion VII₱215.0M64% reported progressHGG BUILDERS48Check in
OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONSTN/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VALLADOLID SECTION, LOBOC, BOHOLRegion VII₱214.7M67% reported progressHGG BUILDERS49Check in
OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONSTN/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, UGPONG SECTION, LOBOC, BOHOLRegion VII₱214.5M62% reported progressSUPREME ABF CONST49Check in
OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOLRegion VII₱213.9M63% reported progressELITE GEN CONTRACTOR AND DEVELOPMENT CORP49Check in
CSSP , SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT CAMANCHILLES RIVER, BRGY.TALAVERA, TOLEDO CITY, CEBURegion VII₱212.3MReported completeJJ &J CONST & GEN SUPPLY22Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF MANSALAY COASTAL ROAD, DEL MUNDO SECTION, MANSALAY, ORIENTAL MINDORORegion IV-B₱212.3MReported completeEGB CONST CORP FORMERLY: EGB CONST191Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, BARANGAY BALUD TO BARANGAY STA. ELENA, TANAUAN, LEYTE, LEYTE 1ST LDRegion VIII₱212.2M94% reported progressEZJONES CONST INC138Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG CARATAO RIVER, BULALACAO, OR. MINDORORegion IV-B₱209.5M9% reported progressG C I CONST AND DEV'T CORP166Check in
SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA./FACILITIES-CONST. OF ROAD DIKE/ESPLANADE ALONG PATRICK RIVER, BRGY. TAGUMPAY SECT., SABLAYAN, OCC. MINDORORegion IV-B₱209.3M94% reported progressSUNWEST INC FORMERLY: SUNWEST CONST183Check in
CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CALOGCOG RIVER (UPSTREAM), BARANGAY CALOGCOG TO BARANGAY MOHON TO BARANGAY ATIPOLO, TANAUAN, LEYTERegion VIII₱207.1M27% reported progressEZJONES CONST INC139Check in
SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, BRGY. MULAWIN (UPSTREAM), NAUJAN, OR. MINDORORegion IV-B₱204.8M87% reported progressSUNWEST INC FORMERLY: SUNWEST CONST231Check in
CONSTRUCTION OF SEAWALL/ESPLANADE INCLUDING ACCESS ROAD ALONG BARANGAY COMON - SAN PEDRO COASTAL ROAD LEADING TO SAN JOSE PORT AND BEACHES, RESORTS AND SUNSET VIEWING, SAN JOSE, ANTIQUERegion VI₱204.5MReported completeA M ORETA & CO INC 10821Check in
Construction of Flood Control Structure along Cavillan River Upstream, Bulalacao, Oriental MindoroBULALACAO (SAN PEDRO) (ORIENTAL MINDORO), ORIENTAL MINDORO₱202.6MReported completeAMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP171Check in
OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TIPOLO RIVER, PHASE 4, MANDAUE CITYRegion VII₱202.5M45% reported progressQUIRANTE CONST CORP FORMERLY: QUIRANTE CONST22Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF SOUTHERN MINDORO COASTAL ROAD, BONGABONG, ORIENTAL MINDORORegion IV-B₱200.1M90% reported progressANORE CONST216Check in
CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURE AT BARANGAY PITOGO, CARLOS P. GARCIA, BOHOLRegion VII₱197.6M82% reported progressCEBU 7H TECHNOCHEM INDUSTRIES INC20Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM), TACLOBAN CITY, LEYTERegion VIII₱197.5M86% reported progressEZJONES CONST INC158Check in
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MANTICAO RIVER (DOWNSTREAM OF MANTICAO BRIDGE), MANTICAO, MISAMIS ORIENTALRegion X₱195.9MReported completePYRAMID CONSOLIDATED BUILDERS & GEN MDSE170Check in
CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, BRGY. STA. ELENA, TANAUAN, LEYTERegion VIII₱195.6M40% reported progressEZJONES CONST INC135Check in
CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS AT SIPALAY RIVERRegion VI₱195.5MReported completeWTG CONST82Check in
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD CONTROL STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, BRGY. MULAWIN (DOWNSTREAM), NAUJAN, OR. MINDORORegion IV-B₱195.3M93% reported progressSUNWEST INC FORMERLY: SUNWEST CONST233Check in
Share card: Koto (Verbena) 2025: flood-control projects in its path

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Track: IBTrACS v04r01, NOAA National Centers for Environmental Information (Knapp et al., 2010), including JTWC data. Recent storms use provisional tracks that may change. Local name assigned by PAGASA. Projects: DPWH flood-control project list; distance is from the project’s reported coordinates to the track line.