| DESIGN AND BUILD OF COASTAL DIKE AND DRAINAGE IMPROVEMENT, CATBALOGAN CITY, SAMAR | Flood Control Management Cluster | ₱744.4M | 87% reported progress | HI-TONE CONST & DEVELOPMENT CORP FORMERLY | 205 | Check in |
| METRO CEBU FLOOD CONTROL PROJECT AND DRAINAGE IMPROVEMENT PROJECT - SUBANG DAKU, LAHUG, GUADALUPE, KINALUMSAN, TIPOLO, TEJERO AND BULACAO RIVER BASINS, CEBU CITY | Flood Control Management Cluster | ₱684.0M | 91% reported progress | ARN BUILDERS INC FOR: ARN BUILDERS | 13 | Check in |
| METRO CEBU FLOOD CONTROL PROJECT - FLOOD CONTROL AND DRAINAGE IMPROVEMENT PROJECT, KINALUMSAN RIVER, DULJO, LABANGON AND MAMBALING, CEBU CITY | Flood Control Management Cluster | ₱553.8M | 22% reported progress | RAYMAN BUILDERS INC | 21 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LAKE MAINIT - TUBAY RIVER (KALINAWAN - KARAK-AN SECTION), TUBAY, AGUSAN DEL NORTE | Region XIII | ₱465.1M | Reported complete | EQUI-PARCO CONST CO | 23 | Check in |
| CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY, DRAINAGE SYSTEM, CATBALOGAN CITY, INCLUDING ANTIAO RIVER CONTROL, SAMAR PROVINCE | Flood Control Management Cluster | ₱445.3M | Reported complete | MSB VITUG CONST | 204 | Check in |
| CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY DRAINAGE SYSTEM, CATBALOGAN CITY INCLUDING ANTIAO RIVER CONTROL, SAMAR | Flood Control Management Cluster | ₱438.8M | Reported complete | MSB VITUG CONST | 205 | Check in |
| FLOOD RISK MANGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR), JICA LOAN NO. PH-P259, CONTRACT PACKAGE 1 (BONBON-KAUSWAGAN) | Flood Control Management Cluster | ₱371.1M | 86% reported progress | A M ORETA & CO INC 108 | 145 | Check in |
| CONSTRUCTION OF FLOOD CONTROL ALONG SIBALOM RIVER, SIBALOM. ANTIQUE | Region VI | ₱358.0M | 47% reported progress | MAC BUILDERS CORP FORMERLY: MAC BUILDERS DEVELOPMENT CORP | 26 | Check in |
| SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14B, TACLOBAN CITY, LEYTE | Region VIII | ₱313.0M | 0% reported progress | L N R CONST | 151 | Check in |
| SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTE | Region VIII | ₱313.0M | 0% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP | 151 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON | Region IV-B | ₱297.0M | 90% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 207 | Check in |
| 1. CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BURABUD-AN, ABUYOG, LEYTE; 2. CONSTRUCTION OF FLOOD CONTROL STRUCTURE CADAC-AN RIVER, BARANGAY PAGSANG-AN, ABUYOG, LEYTE | Region VIII | ₱294.9M | Reported complete | JUCONS CONST OPC FORMERLY:JUCONS CONST &SUPPLY | 94 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE MUMPONG RIVER, TUBAN-BATONG BUHAY, BRGY. TUBAN, SABLAYAN, OCC. MINDORO | Region IV-B | ₱291.8M | 38% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 174 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, MUMPONG RIVER, TUBAN-STA. LUCIA, BRGY. TUBAN, SABLAYAN, OCC. MINDORO | Region IV-B | ₱291.5M | 37% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 174 | Check in |
| CONSTRUCTION/ IMPROVEMENT OF FLOOD MITIGATION STRUCTURES WITH RECHANNELIZATION ALONG ANDANAN RIVER BANK (DOWNSTREAM), BAYUGAN CITY, AGUSAN DEL SUR | Region XIII | ₱289.5M | Reported complete | ADFIL CORP | 72 | Check in |
| CONSTRUCTION/DESILTATION MAON CATCHMENT AREA - VILLAKANANGA CREEK - CALOT - BONBON CREEK, BUTUAN CITY | Region XIII | ₱289.5M | Reported complete | EQUI-PARCO CONST CO | 60 | Check in |
| CLUSTER 5 - 5.1: CONSTRUCTION OF BUTUAN CITY REVETMENT ALONG AGUSAN RIVER, URDUJA SECTION PACKAGE 1, BUTUAN CITY 5.2: CONSTRUCTION OF BUTUAN CITY REVETMENT ALONG AGUSAN RIVER, URDUJA SECTION PACKAGE 2, BUTUAN CITY | Region XIII | ₱289.5M | Reported complete | EQUI-PARCO CONST CO | 57 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CARMEN PORT, SAN AGUSTIN, ROMBLON | Region IV-B | ₱289.5M | Reported complete | LEGACY CONST CORP FORMERLY: LEGACY CONST | 223 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLON | Region IV-B | ₱289.5M | 57% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 158 | Check in |
| Construction of Dubduban Flood Control Structure, San Agustin, Tablas Island Romblon | ALCANTARA (ROMBLON), ROMBLON | ₱289.5M | Reported complete | LEGACY CONST CORP FORMERLY: LEGACY CONST | 218 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MONGPONG, BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORO | Region IV-B | ₱289.5M | Reported complete | LEGACY CONST CORP FORMERLY: LEGACY CONST | 167 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD AND CAUSEWAY FOR TOURISM ALONG AZAGRA PORT, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON | Region IV-B | ₱289.5M | Reported complete | ST TIMOTHY CONST CORP | 197 | Check in |
| Construction of Flood Control Structure (River Training Works) along Mompong River (Downstream), Sablayan, Occidental Mindoro | SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱289.5M | Reported complete | GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC | 168 | Check in |
| CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1 | Region IV-B | ₱289.5M | 62% reported progress | ST TIMOTHY CONST CORP | 227 | Check in |
| Construction of Road Dike/Esplanade along Pangalaan River (Left Side), Naujan, Oriental Mindoro | NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO | ₱289.5M | Reported complete | ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP | 235 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CAJIDIOCAN PORT, SIBUYAN ISLAND, ROMBLON | Region IV-B | ₱289.5M | Reported complete | ST TIMOTHY CONST CORP | 207 | Check in |
| Construction of Road Dike/Esplanade along Sitio Anduyanan, Paluan, Occidental Mindoro | PALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱289.5M | Reported complete | AMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP | 211 | Check in |
| Construction of Paluan Shore Protection and Causeway Development, Sitio Ipol Section, Occidental Mindoro | PALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱289.5M | Reported complete | D T RECIO INC | 209 | Check in |
| SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY FOR TOURISM ALONG AMBULONG PORT, MAGDIWANG, SIBUYAN ISLAND, ROMBLON | Region IV-B | ₱289.5M | Reported complete | ST PIUS CONST AND SUPPLY | 219 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG POBLACION SAN FERNANDO, SIBUYAN ISLAND, ROMBLON | Region IV-B | ₱289.5M | Reported complete | ST TIMOTHY CONST CORP | 199 | Check in |
| Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, Romblon | SAN ANDRES (ROMBLON), ROMBLON | ₱289.5M | Reported complete | YPR GEN CONTRACTOR AND CONST SUPPLY INC | 209 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SABLAYAN PORT, ROMBLON, ROMBLON | Region IV-B | ₱289.5M | Reported complete | ST PIUS CONST AND SUPPLY | 215 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PHASE I, NAUJAN, OR. MINDORO | Region IV-B | ₱287.2M | 86% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 228 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. VICTORIA SECTION, PHASE III, SABLAYAN, OCC. MINDORO | Region IV-B | ₱287.1M | 85% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 183 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ODIONGAN RIVER, PACKAGE 3, GINGOOG CITY, MISAMIS ORIENTAL | Region X | ₱286.3M | Reported complete | VICENTE T LAO CONST | 87 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE-LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE 1 & 2, URBAN DRAINAGE SYSTEM IN BUTUAN CITY (MANDACPAN-BONBON CHANNEL IMPROVEMENT, DOWNSTREAM), PACKAGE 3, BUTUAN CITY | Region XIII | ₱285.7M | 70% reported progress | EQUI-PARCO CONST CO | 60 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE-LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE 1 & 2, URBAN DRAINAGE SYSTEM IN BUTUAN CITY (MANDACPAN-BONBON CHANNEL IMPROVEMENT, DOWNSTREAM), PACKAGE 4, BUTUAN CITY | Region XIII | ₱285.7M | 70% reported progress | EQUI-PARCO CONST CO | 60 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG RIVER, SITIO KULI-KULI SECTION (RS), ARMADO, STA. 000+234-STA. 000+900, ABRA DE IL | Region IV-B | ₱284.3M | 30% reported progress | D T RECIO INC | 209 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. CENTRAL-BRGY. SAN AGUSTIN, STA. 000+240-STA. 000+735.5 (LEFT SIDE), SAN JOSE, OCC. MIND | Region IV-B | ₱284.2M | 65% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 167 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. BATASAN, STA. 000+000-STA. 000+473.35, SAN JOSE, OCC. MINDORO | Region IV-B | ₱284.2M | 65% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 173 | Check in |
| Construction of Flood Control Structure at Tagoloan River, Package 6, Misamis Oriental | TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL | ₱282.3M | Reported complete | RAMISES CONST / EQUI-PARCO CONST CO | 136 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 9, MISAMIS ORIENTAL | Region X | ₱282.2M | Reported complete | ME 3 CONST | 136 | Check in |
| Construction of Flood Control Structure at Tagoloan River, Package 8, Misamis Oriental | TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL | ₱280.8M | Reported complete | EQUI-PARCO CONST CO / TRIPARCO DEVELOPMENT CORP | 136 | Check in |
| SUSTAINABLE INFRASTRUCTURE POJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG UBI RIVER, BRGY. TAGUMPAY, PHASE V, NAUJAN, OR. MINDORO | Region IV-B | ₱280.2M | 91% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 230 | Check in |
| SUISTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. VICTORIA SECTION, PHASE I, SABLAYAN, OCC. MINDORO | Region IV-B | ₱280.2M | 84% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 184 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG DULANGAN RIVER, BRGY. EVANGELISTA, PHASE I, NAUJAN, ORIENTAL MINDORO | Region IV-B | ₱280.1M | 78% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 234 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING M,AJOR/STRATEGIC PUBLIC BUILDINGS/FCILITIES- CONST. OF ROAD DIKE ALONG M,AG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PHASE III, NAUJAN, ORIENTAL MINDORO | Region IV-B | ₱280.1M | 89% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 230 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILUITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE IV, NAUJAN, OR. MINDORO | Region IV-B | ₱279.9M | 86% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 232 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PJHASE IV, NAUJAN, ORIENTAL MINDORO | Region IV-B | ₱279.9M | 88% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 230 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD DIKE ALONG PATRICK RIVER, BRGY. TAGUMPAY SECTION, PHASE II, SABLAYAN, OCC. MINDORO | Region IV-B | ₱279.7M | 92% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 183 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PHASE II, NAUJAN, OR. MINDORO | Region IV-B | ₱279.7M | 87% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 229 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. VICTORIA SECTION, PHASE II, SABLAYAN, OCC. MINDORO | Region IV-B | ₱279.6M | 86% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 183 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY.INARAWAN, PHASE II, NAUJAN, OR. MINORTO | Region IV-B | ₱279.4M | 78% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 231 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROADS/BOULEVARD & CAUSEWAY FOR TOURISM ALONG STA. FE PORT, TABLAS ISLAND, ROMBLON | Region IV-B | ₱279.4M | 89% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 170 | Check in |
| Construction of Flood Control Structure at Tagoloan River, Package 7, Misamis Oriental | TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL | ₱279.4M | Reported complete | EQUI-PARCO CONST CO / TRIPARCO DEVELOPMENT CORP | 136 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIP[AG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE I, NAUJAN, ORIENTAL MINDORO | Region IV-B | ₱279.4M | 82% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP | 231 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE III, NAUJAN, OR. MINDORO | Region IV-B | ₱279.2M | 78% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 232 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PATRICK RIVER, BRGY. TAGUMPAY SECTION, PHASE I, SABLAYAN, OCC. MINDORO | Region IV-B | ₱278.8M | 94% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 183 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PATRICK RIVER, SITIO MANAMOK, BRGY. TAGUMPAY, SABLAYAN, OCC. MINDORO | Region IV-B | ₱277.8M | 37% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 183 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PATRICK RIVER, OLD TAGUMPAY, BRGY. TAGUMPAY, SABLAYAN, OCC. MINDORO | Region IV-B | ₱277.5M | 37% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 183 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (UPSTREAM), SAN JOSE, OCC. MINDORO | Region IV-B | ₱276.6M | 61% reported progress | D T RECIO INC | 160 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (DOWNSTREAM), SAN JOSE, OCC. MINDORO | Region IV-B | ₱276.4M | 59% reported progress | D T RECIO INC | 160 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG PANGALAAN RIVER, (LEFT SIDE), BRGY. SAMPAGUITA, NAUJAN, OR. MINDORO | Region IV-B | ₱276.2M | 24% reported progress | LE BRON CONST | 238 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (DOWNSTREAM LS), PACKAGE C, NAUJAN, OR. MINDORO | Region IV-B | ₱276.1M | 30% reported progress | ANORE CONST | 239 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, (UPSTREAM), BRGY. MULAWIN-BRGY. DEL PILAR, NAUJAN, | Region IV-B | ₱276.0M | 32% reported progress | HGG BUILDERS | 234 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (LS), PACKAGE B, NAUJAN, OR. MINDORO | Region IV-B | ₱276.0M | 24% reported progress | ANORE CONST | 239 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. APITONG SECTION (DOWNSTREAM LS), NAUJAN, OR. MINDORO | Region IV-B | ₱275.8M | 61% reported progress | RAYMAN BUILDERS INC | 233 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. ADELA (DOWNSTREAM), RIZAL, OCC.MINDORO | Region IV-B | ₱275.8M | 60% reported progress | D T RECIO INC | 158 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DFIKE, PANGALAAN RIVER, DOWNSTREAM (RIGHT SIDE), PACKAGE A, NAUJAN, OR. MINDORO | Region IV-B | ₱275.7M | 79% reported progress | RAYMAN BUILDERS INC | 240 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. APITONG SECTION (UPSTREAM LS), NAUJAN, OR. MINDORO | Region IV-B | ₱275.6M | 60% reported progress | RAYMAN BUILDERS INC | 232 | Check in |
| REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY | Region VIII | ₱274.3M | 65% reported progress | E M CUERPO INC | 118 | Check in |
| CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PUGAAN RIVER, PACKAGE 5, MISAMIS ORIENTAL | Region X | ₱274.2M | 73% reported progress | EQUI-PARCO CONST CO | 135 | Check in |
| CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PUGAAN RIVER, PACKAGE 6, MISAMIS ORIENTAL | Region X | ₱274.2M | 60% reported progress | EQUI-PARCO CONST CO | 135 | Check in |
| OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (UPSTREAM), LILOAN, CEBU | Region VII | ₱269.2M | 69% reported progress | BNR CONST & DEVELOPMENT CORP | 36 | Check in |
| CONSTRUCTION/ REHABILITATION OF CAGAYAN DE ORO RIVER BASINS, CALA-CALA SECTION, BRGY. MACASANDIG, CAGAYAN DE ORO CITY | Region X | ₱268.0M | Reported complete | ADFIL CORP | 151 | Check in |
| CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL STRUCTURES IN METRO CEBU, BRGY. PASIL AND ERMITA, BRGY. TEJERO AND BRGY. TIPOLO, CEBU CITY | Flood Control Management Cluster | ₱266.6M | Reported complete | MSB VITUG CONST | 17 | Check in |
| Construction of Flood Control Structure at Tagoloan River, Package 10, Misamis Oriental | TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL | ₱266.2M | Reported complete | HAPPY ALL3 BUILDERS CORP / EQUI-PARCO CONST CO | 136 | Check in |
| CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 4+780.00 - STATION 5+480, SECTION 5 PHASE 11, BRGY. STA. CRUZ, TANAUAN, LEYTE | Region VIII | ₱265.3M | Reported complete | SUNWEST INC FORMERLY: SUNWEST CONST | 140 | Check in |
| CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 1+900 - STATION 2+550, SECTION 5 PHASE 9, BRGY. SAN JOAQUIN, PALO, LEYTE | Region VIII | ₱263.4M | Reported complete | WTG CONST | 141 | Check in |
| WIDENING OF BRIDGE - SIBALOM BR. (B00123PN) ALONG ILOILO - ANTIQUE RD | Region VI | ₱259.4M | Reported complete | ADVANCED FOUNDATION CONST SYSTEMS CORP | 17 | Check in |
| CONSTRUCTION OF LOWER AGUSAN RIVER BANK PROTECTION, AGAO - URDUJA - PPA SECTION, BUTUAN CITY, AGUSAN DEL NORTE | Region XIII | ₱250.9M | Reported complete | EQUI-PARCO CONST CO | 57 | Check in |
| REPAIR / REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS AND BRIDGES, FLOOD CONTROL, OTHER PUBLIC | Cebu 7th DEO | ₱250.9M | Reported complete | QM BUILDERS | 54 | Check in |
| Construction of Road Dike along Bucayao River (East Side), Sitio Malaya Section, Barangay Tagumpay, Naujan, Oriental Mindoro | NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO | ₱247.5M | Reported complete | ST TIMOTHY CONST CORP | 228 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLON | Region IV-B | ₱247.5M | 93% reported progress | YPR GEN CONTRACTOR AND CONST SUPPLY INC | 187 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAY | Region IV-B | ₱247.5M | 94% reported progress | YPR GEN CONTRACTOR AND CONST SUPPLY INC | 187 | Check in |
| Construction of Road Dike along Bucayao River (East Side), Sitio Malinao Section, Barangay Tagumpay, Naujan, Oriental Mindoro | NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO | ₱247.5M | Reported complete | ELITE GEN CONTRACTOR AND DEVELOPMENT CORP | 227 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF LIGAYA-STA. LUCIA COASTAL ROAD (STA. LUCIA SECTION), SABLAYAN, OCC. MINDORO | Region IV-B | ₱247.5M | 79% reported progress | ANORE CONST | 165 | Check in |
| Construction of Road Dike aling Mag-asawang Tubig River, Sampaloc Section, Barangay Sto. Niño, Naujan, Oriental Mindoro | NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO | ₱247.5M | Reported complete | RAYMAN BUILDERS INC | 237 | Check in |
| Construction of Road Dike along Mag-asawang Tubig River, Dayapan Section, Barangay Sto. Niño, Naujan, Oriental Mindoro | NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO | ₱247.5M | Reported complete | RAYMAN BUILDERS INC | 236 | Check in |
| OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST OF LOBOC RIVER CONTROL STRUCTURE, UGPONG SECTION TO VILLAFLOR SECTION, LEFT SI | Region VII | ₱241.2M | 83% reported progress | SUPREME ABF CONST | 49 | Check in |
| OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION SAWANG, RIGHT SIDE PHASE 1, LOBOC, | Region VII | ₱241.2M | 80% reported progress | HGG BUILDERS | 48 | Check in |
| OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION ONDOL, RIGHT SIDE, LOBOC, BOHOL | Region VII | ₱241.2M | 78% reported progress | HGG BUILDERS & SUPPLY | 49 | Check in |
| CONSTRUCTION OF JALIOBONG-SAN ISIDRO RIVER CONTROL PROJECT, KITCHARAO, AGUSAN DEL NORTE | Region XIII | ₱241.2M | Reported complete | ADFIL CORP | 12 | Check in |
| CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (MAHAY - VIADUCT SECT), BUTUAN CITY, AGUSAN DEL NORTE | Region XIII | ₱241.2M | Reported complete | TRIPARCO DEVELOPMENT CORP | 57 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF TUGDAN CAUSEWAY, ALCANTARA, TABLAS ISLAND, ROMBLON | Region IV-B | ₱241.2M | Reported complete | LEGACY CONST CORP FORMERLY: LEGACY CONST | 190 | Check in |
| CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES AND CHANNELIZATION, FATIMA, DULAG, LEYTE 2ND LD, DULAG, LEYTE | Region VIII | ₱241.2M | Reported complete | EZJONES CONST INC | 120 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURES ALONG BALETE RIVER, PHASE 2, BRGY. PAPANDUNGIN, GLORIA, OR. MINDORO | Region IV-B | ₱241.2M | 71% reported progress | EIGHT J'S CONST SERVICES | 233 | Check in |
| SUSTAINABLE INFRASTCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLI BUILDINGS/FACILITIES- CONST. OF TABLAS EAST COAST BOULEVARD, SANTA MARIA, TABLAS ISLAND, ROMBLON | Region IV-B | ₱241.2M | Reported complete | LEGACY CONST CORP FORMERLY: LEGACY CONST | 198 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, PHASE 1, BRGY. PAPANDUNGIN, GLORIA, OR. MINDORO | Region IV-B | ₱241.2M | 76% reported progress | NEW RICH GEN CONTRACTOR SERVICES & TRADING CO INC | 233 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER, BRGY. MAOYON (LS), PTO. PRINCESA CITY, PALAWAN | Region IV-B | ₱241.2M | 94% reported progress | MAMSAR CONST AND INDUSTRIAL CORP | 194 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, BRGY. BALETE, GLORIA, OR. MINDORIO | Region IV-B | ₱241.2M | 82% reported progress | EIGHT J'S CONST SERVICES | 233 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, BRGY. BALETE - BRGY. PAPANDUNGIN, GLORIA, ORIENTAL MINDORO | Region IV-B | ₱241.2M | 81% reported progress | EIGHT J'S CONST SERVICES | 233 | Check in |
| Construction of Flood Control Structure along Abra de Ilog River, Sitio Kuli-Kuli Section, Armado, Abra de Ilog, Occidental Mindoro | ABRA DE ILOG (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱241.2M | Reported complete | GOLDEN J'S CONST SERVICES | 209 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 1, BRGY. SAN VICENTE, SANTA CRUZ, OC | Region IV-B | ₱241.2M | Reported complete | SILVERWOLVES CONST CORP | 203 | Check in |
| Construction of Road Dike/Esplanade along Pangalaan River (Right Side), Naujan, Oriental Mindoro | NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO | ₱241.2M | Reported complete | GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC | 238 | Check in |
| Construction of Road Dike/Esplanade along Sitio Katanlawan, Paluan, Occidental Mindoro | PALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱241.2M | Reported complete | ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP | 210 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENAMNCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER (RS), STA. 000+000-STA. 000+623.17, PTO. PRINCESA CITY, PALAWAN | Region IV-B | ₱241.2M | 96% reported progress | MAMSAR CONST AND INDUSTRIAL CORP | 195 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 2, BRGY. SAN VICENTE, SANTA CRUZ, OC | Region IV-B | ₱241.2M | Reported complete | SILVERWOLVES CONST CORP | 202 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURE PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIVER CONTROL STRUCTURE ALONG MAYHA-TULAY RIVER, ODIONGAN, ROMBLON | Region IV-B | ₱241.2M | 83% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 192 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. CARMEN SECTION, SAN AGUSTIN, TABLAS ISLAND, ROMBLON | Region IV-B | ₱241.2M | 87% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 223 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF COASTAL ROAD, PHASE 2, STA. FE, TABLAS ISLAND, ROMBLON | Region IV-B | ₱241.2M | 93% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 169 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG RIVER, PERLAS SECTION, WAWA, ABRA DE ILOG, OCC. MINDORO | Region IV-B | ₱241.2M | 83% reported progress | ST TIMOTHY CONST CORP | 229 | Check in |
| Construction of Paluan Shore Protection and Causeway Development, Sitio Malugao Section, Occidental Mindoro | PALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱241.2M | Reported complete | D T RECIO INC | 209 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF DUBDUBAN FLOOD CONTROL STRUCTURE (DOWNSTREAM), SAN AGUSTIN, TABLAS ISLAND, ROMBLON | Region IV-B | ₱241.2M | 82% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 218 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF DUBDUBAN FLOOD CONTROL STRUCTURE (UPSTREAM), SAN AGUSTIN, TABLAS ISLAND, ROMBLON | Region IV-B | ₱241.2M | 87% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 217 | Check in |
| Construction of Flood Control Structure along Abra de Ilog River, Cabacao Section, Abra de Ilog, Occidental Mindoro | ABRA DE ILOG (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱241.2M | Reported complete | GOLDEN J'S CONST SERVICES | 213 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 1, BRGY. MULAWIN, NAUJAN, OR. MINDORO | Region IV-B | ₱239.3M | 35% reported progress | HGG BUILDERS | 233 | Check in |
| CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 2+550 - STATION 3+180, SECTION 5 PHASE 10, BRGY. SAN JOAQUIN, PALO, LEYTE | Region VIII | ₱239.0M | Reported complete | SUNWEST INC FORMERLY: SUNWEST CONST | 141 | Check in |
| CONSTRUCTION OF RIVER FLOOD MITIGATION STRUCTURE ALONG HANAGDONG BRIDGE, SURIGAO-AGUSAN WEST COASTAL ROAD, SURIGAO DEL NORTE | Region XIII | ₱238.8M | 46% reported progress | TRIPARCO DEVELOPMENT CORP | 1 | Check in |
| CONSTRUCTION OF LINONGGANAN RIVER FLOOD CONTROL ALONG SURIGAO-AGUSAN WEST COASTAL ROAD, BRGY. LINONGGANAN, SAN FRANCISCO, SURIGAO DEL NORTE | Region XIII | ₱238.6M | 19% reported progress | TRIPARCO DEVELOPMENT CORP | 11 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ILVITA RIVERBANK PROTECTION WORKS ALONG AMNAY RIVER (DOWNSTREAM), SABLAYAN, OCC. MINDORO | Region IV-B | ₱238.3M | 80% reported progress | ANORE CONST | 186 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 11, MISAMIS ORIENTAL | Region X | ₱237.6M | 61% reported progress | RAMISES CONST | 136 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 13, MISAMIS ORIENTAL | Region X | ₱237.6M | 61% reported progress | TRIPARCO DEVELOPMENT CORP | 136 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 14, MISAMIS ORIENTAL | Region X | ₱237.6M | 61% reported progress | EQUI-PARCO CONST CO | 136 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAGOLOAN RIVER, PACKAGE 12, MISAMIS ORIENTAL | Region X | ₱237.6M | 65% reported progress | EQUI-PARCO CONST CO | 136 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, BRGY. CANUBING II (DOWNSTREAM), STA. 000+320-STA. 000+613.90, CALAPAN, OR. MINDORO | Region IV-B | ₱237.0M | 52% reported progress | ADSL CONST & TRADING | 236 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADFE ALONG PATRICK RIVER (UPSTREAM), BRGY. SAN FRANCISCO-BRGY. PAETAN SECTION, STA. 000+668.34-STA. 001+000 ( | Region IV-B | ₱236.9M | 9% reported progress | SILVERWOLVES CONST CORP | 187 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, BRGY. CANUBING II, STA. 000+000-STA. 000+305.50, CALAPAN, OR. MINDORO | Region IV-B | ₱236.9M | 38% reported progress | ADSL CONST & TRADING | 236 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG PATRICK RIVER (UPSTREAM), BRGY. PAETAN-BRGY. TAGUMPAY, STA.01+010-STA. 001+335.99 (LEFT SIDE), SAB | Region IV-B | ₱236.9M | 64% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 187 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIVERBANK PROTECTION WORKS ALONG LABANGAN RIVER (UPSTREAM), BRGY. MURTHA, STA. 000+000-STA. 000+465.82, SAN JOSE, OCC. MINDOR | Region IV-B | ₱236.9M | 71% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 168 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC B UILDINGS/FACILITIES- CONST. OF RIVERBANK PROTECTION WORKS ALONG LABANGAN RIVER (DOWNSTREAM), BRGY. MURTHA, STA. 000+480-STA. 000+921.80, SAN JOSE, OCC. MIN | Region IV-B | ₱236.9M | 71% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 168 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG PATRICK RIVER (DOWNSTREAM), BRGY. PAETAN-BRG. TAGUMPAY, STA. 001+345-STA. 001+639.06 (LEFT SIDE), S | Region IV-B | ₱236.9M | 62% reported progress | LEGACY CONST CORP FORMERLY: LEGACY CONST | 187 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. AMBULONG SECTION, MAGDIWANG, SIBUYAN ISLAND, ROMBLON | Region IV-B | ₱236.4M | Reported complete | YPR GEN CONTRACTOR AND CONST SUPPLY INC | 219 | Check in |
| OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, TAMBANGAN SECTION (LEFT SIDE), LOAY, BOHOL | Region VII | ₱236.4M | 0% reported progress | SUPREME ABF CONST & CONST SUPPLY CO INC | 51 | Check in |
| OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, TAMBANGAN SECTION (RIGHT SIDE), LOAY, BOHOL | Region VII | ₱236.3M | 0% reported progress | SUPREME ABF CONST | 51 | Check in |
| CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM ALONG BANGON RIVER, PHASE 3, BARANGAY SAN JOSE, PALO, LEYTE | Region VIII | ₱236.2M | 20% reported progress | EZJONES CONST INC | 143 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM), PHASE 2, TACLOBAN CITY | Region VIII | ₱236.1M | 31% reported progress | EZJONES CONST INC | 158 | Check in |
| BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE, BALETE RIVER, BRGY. PAPANDUNGIN, GLORIA, OR. MINDORO | Region IV-B | ₱236.1M | 71% reported progress | ALRIE CONST SERVICES | 232 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 2, BRGY. SAN LUIS, NAUJAN, OR. MINDOR | Region IV-B | ₱234.3M | 87% reported progress | GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC | 232 | Check in |
| CLUSTER 1: 1. CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE A). SITIO BAGANG, BRGY. CABACUNGAN, DULAG, LEYTE 2. CONSTRUCTION (EXTENSION) OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE A), BRGY. FATIMA, DULAG, LEYTE | Region VIII | ₱233.5M | Reported complete | EZJONES CONST INC | 120 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD DIKE/ESPLANADE ALONG BUSUANGA RIVER, BRGY. AGUAS, RIZAL, OCC. MINDO | Region IV-B | ₱232.8M | 88% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 173 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG BUSUANGA RIVER, BRGY. PITOGO, RIZAL, OCC. MINDOR | Region IV-B | ₱232.8M | 82% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 172 | Check in |
| FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG, SITIO KALINYAWAN SECTION, SAN VICENTE, ABRA DE ILOG, OCC. MINDORO | Region IV-B | ₱232.6M | 72% reported progress | ANORE CONST | 219 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC | Region IV-B | ₱232.4M | 90% reported progress | ELITE GEN CONTRACTOR AND DEVELOPMENT CORP | 160 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE I, BRGY. SAN LUIS, NAUJAN, OR. MINDOR | Region IV-B | ₱232.4M | 82% reported progress | NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST | 232 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. ADELA, SAN JOSE, OCC. MINDORO | Region IV-B | ₱232.4M | 85% reported progress | YPR GEN CONTRACTOR AND CONST SUPPLY INC | 158 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BONGABONG RIVER, BRGY. LISAP-BRGY. BATANGAN (UPSTREAM), STA. 000+330-STA. 000+649.50, BONGABONG, OR. MINDOR | Region IV-B | ₱231.5M | 28% reported progress | JJPR CONST SERVICES | 204 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURES, MOMPONG RIVER, BRGY. SANTA LUCIA (UPSTREAM-RS), SABLAYAN, OCC. MINDORO | Region IV-B | ₱231.3M | 30% reported progress | ANORE CONST | 169 | Check in |
| CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (UPSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | ₱231.2M | 0% reported progress | GOLDEN J'S CONST SERVICES | 232 | Check in |
| FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BONGABONG RIVER, BRGY. LISAP-BRGY. BATANGAN (DOWNSTREAM), STA. 000+680-STA. 000+995.85, BONGABONG, O. | Region IV-B | ₱231.1M | 45% reported progress | JIIK CONST SERVICES | 204 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE WITH ESPLANADE ALONG POLA RIVER, BRGY. LUMANGBAYAN SECTION (UPSTREAM/LS), STA. CRUZ, OCC. MINDORO | Region IV-B | ₱231.1M | 60% reported progress | D T RECIO INC | 192 | Check in |
| CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (DOWNSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | ₱231.0M | 0% reported progress | GOLDEN J'S CONST SERVICES | 232 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE WITH ESPLANADE ALONG POLA RIVER, BRGY. LUMANGBAYAN SECTION (DOWNSTREAM/LS), STA. CRUZ, OCC. MINDORO | Region IV-B | ₱231.0M | 60% reported progress | D T RECIO INC | 191 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, MOMPONG RIVER,BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORO | Region IV-B | ₱230.2M | 61% reported progress | ANORE CONST | 168 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BANSUD RIVER, BRGY. CONRAZON, BANSUD, OR. MINDORO | Region IV-B | ₱230.1M | 59% reported progress | LE BRON CONST | 223 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, (UPSTREAM, RIGHT SIDE), BRGY. BALETE, GLORIA, OR. MINDORO | Region IV-B | ₱230.1M | 46% reported progress | ALRIE CONST SERVICES | 234 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF RIVERSIDE PROTECTION STRUCTURE, PILI RIVER, UPSTREAM, POBLACION, SAN FERNANDO, SIBUYAN ISLAND, ROMBLON | Region IV-B | ₱230.1M | 90% reported progress | YPR GEN CONTRACTOR AND CONST SUPPLY INC | 200 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER DOWNSTREAM, GLORIA, OR. MINDORO | Region IV-B | ₱230.1M | 78% reported progress | JIIK CONST SERVICES | 233 | Check in |
| CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG PALUAN RIVER, BRGY. SAN JOSE POBLACION (BRGY. 6) SECTION (L/S), PALUAN, OCC. MINDORO | Region IV-B | ₱230.1M | 43% reported progress | ANORE CONST | 209 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG PANGALAAN RIVER, BRGY. SAMPAGUITA, PHASE 2, NAUJAN, OR. MINDORO | Region IV-B | ₱230.0M | 25% reported progress | LE BRON CONST | 239 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, (DOWNSTREAM, RIGHT SIDE), BRGY. BALETE, GLORIA, OR. MINDORO | Region IV-B | ₱230.0M | 43% reported progress | JIIK CONST SERVICES | 234 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BALETE RIVER, (UPSTREAM, LEFT SIDE), BRGY. BALETE, GLORIA, OR. MINDORO | Region IV-B | ₱230.0M | 45% reported progress | ALRIE CONST SERVICES | 234 | Check in |
| CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG PALUAN RIVER, BRGY. SAN JOSE POBLACION (BRGY. 6) SECTION (R/S), PALUAN, OCC. MINDORO | Region IV-B | ₱230.0M | 42% reported progress | ANORE CONST | 209 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BANSUD RIVER BRGY. CONRAZON (UPSTREAM), BANSUD, OR. MINDORO | Region IV-B | ₱230.0M | 61% reported progress | LE BRON CONST | 223 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, (DOWNSTREAM), BRGY. MULAWIN-BRGY. DEL PILAR, NAUJAN, OR. MINDORO | Region IV-B | ₱230.0M | 34% reported progress | HGG BUILDERS | 234 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BONGABONG RIVER, BONGABONG, OR. MINDORO | Region IV-B | ₱229.9M | 42% reported progress | JJPR CONST SERVICES | 204 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN-BRGY. SAMPAGUITA (UPSTREAM), PACKAGE A, NAUJAN, OR. MINDORO | Region IV-B | ₱229.9M | 70% reported progress | RAYMAN BUILDERS INC | 240 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN-BRGY. SAMPAGUITA, PACKAGE B, NAUJAN, OR. MINDORO | Region IV-B | ₱229.9M | 25% reported progress | RAYMAN BUILDERS INC | 241 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BONGABONG RIVER UPSTREAM, BONGABONG, OR. MINDORO | Region IV-B | ₱229.8M | 32% reported progress | JJPR CONST SERVICES | 204 | Check in |
| FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF RIVERSIDE PROTECTION STRUCTURE, DOWNSTREAM, BRGY. PUNONG, SAN FERNANDO, ROMBLON | Region IV-B | ₱229.8M | 88% reported progress | YPR GEN CONTRACTOR AND CONST SUPPLY INC | 206 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. SAMPAGUITA (DOWNSTREAM), NAUJAN, OR. MINDORO | Region IV-B | ₱229.6M | 60% reported progress | RAYMAN BUILDERS INC | 239 | Check in |
| Construction of Basey Tide Embankment, Basey, Samar | SAMAR (WESTERN SAMAR) | ₱227.8M | Reported complete | NORTHERN BUILDERS / RIANNE CONST | 158 | Check in |
| Construction of Basey Tide Embankment, Basey, Samar | SAMAR (WESTERN SAMAR) | ₱227.8M | Reported complete | NORTHERN BUILDERS / RIANNE CONST | 158 | Check in |
| Construction of Basey Tide Embankment, Basey, Samar | SAMAR (WESTERN SAMAR) | ₱227.8M | Reported complete | NORTHERN BUILDERS / RIANNE CONST | 158 | Check in |
| CLUSTER 3: 1. CONSTRUCTION OF STORM SURGE PROTECTION: TIDE EMBANKMENT, SUBSECTION 6.8, BARANGAY SAN ROQUE, TANAUAN, LEYTE; 2. CONSTRUCTION OF STORM SURGE PROTECTION: TIDE EMBANKMENT, SUBSECTION 6.9, BARANGAY SAN ROQUE, TANAUAN, LEYTE | Region VIII | ₱226.2M | Reported complete | EZJONES CONST INC | 138 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF BANK PROTECTION STRUCTURE WITH ROAD DIKE ALONG LUMINTAO RIVER, BRGY. MAGSIKAP AND BRGY. MALAWAAN (DOWNSTREAM), RIZAL, OCC. MINDORO | Region IV-B | ₱225.6M | 85% reported progress | AMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP | 163 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROXAS BY-PASS ROAD, ROXAS, OR. MINDORO | Region IV-B | ₱221.9M | 86% reported progress | GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC | 198 | Check in |
| CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF BANK PROTECTION STRUCTURE WITH ROAD DIKE ALONG LUMINTAO RIVER, BRGY. MAGSIKAP (UPSTREAM), RIZAL, OCC. MINDORO | Region IV-B | ₱221.9M | 64% reported progress | D T RECIO INC | 163 | Check in |
| Construction of Road Dike/Esplanade along Patrick River, Sablayan, Occidental Mindoro | SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO | ₱217.1M | Reported complete | SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP | 184 | Check in |
| OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONSTN/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURURE, GOTOZAN SECTION, LOBOC, BOHOL | Region VII | ₱215.0M | 64% reported progress | HGG BUILDERS | 48 | Check in |
| OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONSTN/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VALLADOLID SECTION, LOBOC, BOHOL | Region VII | ₱214.7M | 67% reported progress | HGG BUILDERS | 49 | Check in |
| OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONSTN/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, UGPONG SECTION, LOBOC, BOHOL | Region VII | ₱214.5M | 62% reported progress | SUPREME ABF CONST | 49 | Check in |
| OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOL | Region VII | ₱213.9M | 63% reported progress | ELITE GEN CONTRACTOR AND DEVELOPMENT CORP | 49 | Check in |
| CSSP , SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT CAMANCHILLES RIVER, BRGY.TALAVERA, TOLEDO CITY, CEBU | Region VII | ₱212.3M | Reported complete | JJ &J CONST & GEN SUPPLY | 22 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF MANSALAY COASTAL ROAD, DEL MUNDO SECTION, MANSALAY, ORIENTAL MINDORO | Region IV-B | ₱212.3M | Reported complete | EGB CONST CORP FORMERLY: EGB CONST | 191 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, BARANGAY BALUD TO BARANGAY STA. ELENA, TANAUAN, LEYTE, LEYTE 1ST LD | Region VIII | ₱212.2M | 94% reported progress | EZJONES CONST INC | 138 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG CARATAO RIVER, BULALACAO, OR. MINDORO | Region IV-B | ₱209.5M | 9% reported progress | G C I CONST AND DEV'T CORP | 166 | Check in |
| SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA./FACILITIES-CONST. OF ROAD DIKE/ESPLANADE ALONG PATRICK RIVER, BRGY. TAGUMPAY SECT., SABLAYAN, OCC. MINDORO | Region IV-B | ₱209.3M | 94% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 183 | Check in |
| CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CALOGCOG RIVER (UPSTREAM), BARANGAY CALOGCOG TO BARANGAY MOHON TO BARANGAY ATIPOLO, TANAUAN, LEYTE | Region VIII | ₱207.1M | 27% reported progress | EZJONES CONST INC | 139 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, BRGY. MULAWIN (UPSTREAM), NAUJAN, OR. MINDORO | Region IV-B | ₱204.8M | 87% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 231 | Check in |
| CONSTRUCTION OF SEAWALL/ESPLANADE INCLUDING ACCESS ROAD ALONG BARANGAY COMON - SAN PEDRO COASTAL ROAD LEADING TO SAN JOSE PORT AND BEACHES, RESORTS AND SUNSET VIEWING, SAN JOSE, ANTIQUE | Region VI | ₱204.5M | Reported complete | A M ORETA & CO INC 108 | 21 | Check in |
| Construction of Flood Control Structure along Cavillan River Upstream, Bulalacao, Oriental Mindoro | BULALACAO (SAN PEDRO) (ORIENTAL MINDORO), ORIENTAL MINDORO | ₱202.6M | Reported complete | AMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP | 171 | Check in |
| OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TIPOLO RIVER, PHASE 4, MANDAUE CITY | Region VII | ₱202.5M | 45% reported progress | QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 22 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF SOUTHERN MINDORO COASTAL ROAD, BONGABONG, ORIENTAL MINDORO | Region IV-B | ₱200.1M | 90% reported progress | ANORE CONST | 216 | Check in |
| CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURE AT BARANGAY PITOGO, CARLOS P. GARCIA, BOHOL | Region VII | ₱197.6M | 82% reported progress | CEBU 7H TECHNOCHEM INDUSTRIES INC | 20 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM), TACLOBAN CITY, LEYTE | Region VIII | ₱197.5M | 86% reported progress | EZJONES CONST INC | 158 | Check in |
| CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MANTICAO RIVER (DOWNSTREAM OF MANTICAO BRIDGE), MANTICAO, MISAMIS ORIENTAL | Region X | ₱195.9M | Reported complete | PYRAMID CONSOLIDATED BUILDERS & GEN MDSE | 170 | Check in |
| CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, BRGY. STA. ELENA, TANAUAN, LEYTE | Region VIII | ₱195.6M | 40% reported progress | EZJONES CONST INC | 135 | Check in |
| CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS AT SIPALAY RIVER | Region VI | ₱195.5M | Reported complete | WTG CONST | 82 | Check in |
| SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD CONTROL STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, BRGY. MULAWIN (DOWNSTREAM), NAUJAN, OR. MINDORO | Region IV-B | ₱195.3M | 93% reported progress | SUNWEST INC FORMERLY: SUNWEST CONST | 233 | Check in |