Flood Control and Drainage24H00001

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION ONDOL, RIGHT SIDE, LOBOC, BOHOL

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION ONDOL, RIGHT SIDE, LOBOC, BOHOL is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱241,249,985.55. Status: Past target date (DPWH On-Going). Contractor on record: HGG BUILDERS & SUPPLY 17824. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 17824

18 projects · ₱2.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TALISAY RIVER, PACKAGE 2, BARANGA

Region V, Region V

2025₱237.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TALISAY RIVER, BARANGAY CAHABAAN,

Region V, Region V

2025₱234.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TALISAY RIVER, BARANGAY BINA

Region V, Region V

2024₱234.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES-CONSTRUCTION OF CAMARINES NORTE PROVINCIAL HOSPITAL, DAET, CAMARINES NORTE

Region V, Region V

2024₱216.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN RIVER, BARANGAY CALINGATNAN - SITIO MINAELI, BORONGAN CITY, EASTERN SAMAR

Region VIII, Region VIII

2024₱192.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, PAMPLONA, DEL GALLEGO, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱138.9M
Past target date (DPWH On-Going)
View all 18 projects →

4. Implementation

Contract Amount

₱241,249,985.55

Progress

Past target date (DPWH On-Going)

Start Date

April 5, 2024

Target End

September 19, 2025

5. Audit