Construction of Revetment23E00131

Construction of Sta Cruz Seawall, Barangay Tagum - Barangay Morales Section, Sta Cruz, Marinduque

Construction of Sta Cruz Seawall, Barangay Tagum - Barangay Morales Section, Sta Cruz, Marinduque is a DPWH-tracked public work in SANTA CRUZ (MARINDUQUE), MARINDUQUE, Region IV-B. Reported contract value: ₱241,247,258.70. Status: Reported complete (DPWH). Contractor on record: HGG BUILDERS & SUPPLY. Figures trace to sumbong.

SANTA CRUZ (MARINDUQUE), MARINDUQUE, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Banto, Mogpog, Marinduque
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Marinduque District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱241,247,258.70

Progress

Reported complete (DPWH)

Start Date

April 13, 2023

Target End

May 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.