Flood Control and Drainage23G00062

CONSTRUCTION OF FLOOD CONTROL ALONG SIBALOM RIVER, SIBALOM. ANTIQUE

CONSTRUCTION OF FLOOD CONTROL ALONG SIBALOM RIVER, SIBALOM. ANTIQUE is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱358,049,202.47. Status: Past target date (DPWH On-Going). Contractor on record: MAC BUILDERS CORP FORMERLY: MAC BUILDERS DEVELOPMENT CORP. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱358,049,202.47

Progress

Past target date (DPWH On-Going)

Start Date

April 20, 2023

Target End

February 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.