Construction of Flood Mitigation Structure24E00118

Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, Romblon

Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, Romblon is a DPWH-tracked public work in SAN ANDRES (ROMBLON), ROMBLON, Region IV-B. Reported contract value: ₱289,492,750.90. Status: Reported complete (DPWH). Contractor on record: YPR GEN CONTRACTOR AND CONST SUPPLY INC. Figures trace to sumbong.

SAN ANDRES (ROMBLON), ROMBLON, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canlumay Flood Control Structure, Odiongan, Romblon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008382

₱1,788,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0005017

₱602,194.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0018713

₱172,611.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008396

₱165,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004006

₱99,740.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱289,492,750.90

Progress

Reported complete (DPWH)

Start Date

March 2, 2024

Target End

February 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.