GAA 2025 OO-225I00080

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, BRGY. STA. ELENA, TANAUAN, LEYTE

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, BRGY. STA. ELENA, TANAUAN, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱195,620,356.39. Status: Past target date (DPWH On-Going). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱195,620,356.39

Progress

Past target date (DPWH On-Going)

Start Date

May 14, 2025

Target End

May 8, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.