GAA 2025 OO-225H00049

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (UPSTREAM), LILOAN, CEBU

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (UPSTREAM), LILOAN, CEBU is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱269,175,374.44. Status: Past target date (DPWH On-Going). Contractor on record: BNR CONST & DEVELOPMENT CORP. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱269,175,374.44

Progress

Past target date (DPWH On-Going)

Start Date

April 11, 2025

Target End

May 5, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.