Flood Control and Drainage25E00029

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE WITH ESPLANADE ALONG POLA RIVER, BRGY. LUMANGBAYAN SECTION (UPSTREAM/LS), STA. CRUZ, OCC. MINDORO

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE WITH ESPLANADE ALONG POLA RIVER, BRGY. LUMANGBAYAN SECTION (UPSTREAM/LS), STA. CRUZ, OCC. MINDORO is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱231,106,025.22. Status: Past target date (DPWH On-Going). Contractor on record: D T RECIO INC. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

43 projects · ₱5.9B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM- REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE- SECONDARY ROADS- MARINDUQUE CIRCUMFERENTIAL ROAD- K0021+500-K0021+800, MARINDUQUE

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USE'S CHANGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY STRUCTURE ALONG MINDORO WEST COASTAL ROAD, K0229+(-871)-K0263+000 (INTERMITTENT SECTIONS), OCCIDENTAL MINDORO

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)

Construction of Paluan Shore Protection and Causeway Development, Sitio Ipol Section, Occidental Mindoro

PALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG RIVER, SITIO KULI-KULI SECTION (RS), ARMADO, STA. 000+234-STA. 000+900, ABRA DE IL

Region IV-B, Region IV-B

2025₱284.3M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (UPSTREAM), SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2025₱276.6M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (DOWNSTREAM), SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2025₱276.4M
Past target date (DPWH On-Going)
View all 43 projects →

4. Implementation

Contract Amount

₱231,106,025.22

Progress

Past target date (DPWH On-Going)

Start Date

February 15, 2025

Target End

February 9, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.