Construction of Flood Mitigation Structure24E00051

Construction of Road Dike along Mag-asawang Tubig River, Dayapan Section, Barangay Sto. Niño, Naujan, Oriental Mindoro

Construction of Road Dike along Mag-asawang Tubig River, Dayapan Section, Barangay Sto. Niño, Naujan, Oriental Mindoro is a DPWH-tracked public work in NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱247,495,045.00. Status: Reported complete (DPWH). Contractor on record: RAYMAN BUILDERS INC. Figures trace to sumbong.

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation along Bucayao River Sitio Barucan, Brgy. San Luis, Naujan, Oriental Mindoro
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008378

₱1,267,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004239

₱1,035,174.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0001426

₱2,931,832.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008390

₱117,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004240

₱92,822.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0001427

₱270,752.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

26 projects · ₱7.6B total · 0 flags

4. Implementation

Contract Amount

₱247,495,045.00

Progress

Reported complete (DPWH)

Start Date

March 9, 2024

Target End

March 3, 2025

5. Audit