Flood Control and Drainage25E00269

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BONGABONG RIVER, BRGY. LISAP-BRGY. BATANGAN (DOWNSTREAM), STA. 000+680-STA. 000+995.85, BONGABONG, O.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BONGABONG RIVER, BRGY. LISAP-BRGY. BATANGAN (DOWNSTREAM), STA. 000+680-STA. 000+995.85, BONGABONG, O. is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱231,114,686.03. Status: Past target date (DPWH On-Going). Contractor on record: JIIK CONST SERVICES. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

49 projects · ₱5.9B total · 2 flags

4. Implementation

Contract Amount

₱231,114,686.03

Progress

Past target date (DPWH On-Going)

Start Date

March 12, 2025

Target End

March 6, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.