Roads16AB0006

PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT & MANAGEMENT - 4 (HDM-4), ILOCOS NORTE-APAYAO ROAD, K0499+(-348) -K0499+000, K0500+863 - K0501+314

PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT & MANAGEMENT - 4 (HDM-4), ILOCOS NORTE-APAYAO ROAD, K0499+(-348) -K0499+000, K0500+863 - K0501+314 is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱6,864,641.83. Status: Reported complete (DPWH). Contractor on record: SOLSONA-GANAL CONST. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control system in Brgy. Valdez, Marcos, Ilocos Norte, 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-16-0038832

₱3,395,952.00 · FY2016

Released to Central Off (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

31 projects · ₱185.8M total · 0 flags

4. Implementation

Contract Amount

₱6,864,641.83

Progress

Reported complete (DPWH)

Start Date

January 20, 2016

Target End

March 14, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.