Roads24CD0156

CONSTRUCTION OF ROAD, BARANGAY SANTO CRISTO, SAN JOSE DEL MONTE, BULACAN

CONSTRUCTION OF ROAD, BARANGAY SANTO CRISTO, SAN JOSE DEL MONTE, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱48,255,018.82. Status: Reported complete (DPWH). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Poblacion, San Jose del Monte, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0018833

₱7,150,000.00 · FY2024

Released to Surigao del Norte State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱48,255,018.82

Progress

Reported complete (DPWH)

Start Date

April 25, 2024

Target End

April 12, 2025