GAA 2016 MFO-116G00042

WIDENING OF ILOILO - CAPIZ ROAD (NEW ROUTE), POTOTAN - DUENAS SECTION, K0039+000 - K0042+191, K0042+

WIDENING OF ILOILO - CAPIZ ROAD (NEW ROUTE), POTOTAN - DUENAS SECTION, K0039+000 - K0042+191, K0042+ is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱92,019,876.26. Status: Reported complete (DPWH). Contractor on record: F GURREA CONST INC. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱92,019,876.26

Progress

Reported complete (DPWH)

Start Date

March 14, 2016

Target End

June 14, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.