Roads21K00159

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT) CONSTRUCTION OF SOUTHERN BUKIDNON AGRI-INDUSTRIAL ECONOMIC ZONE, ROAD NETWORK DEVELOPMENT PROJECT (PACKAGE 18), KIBAWE-DANGCAGAN, BUKIDNON

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT) CONSTRUCTION OF SOUTHERN BUKIDNON AGRI-INDUSTRIAL ECONOMIC ZONE, ROAD NETWORK DEVELOPMENT PROJECT (PACKAGE 18), KIBAWE-DANGCAGAN, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱78,833,777.88. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱78,833,777.88

Progress

Reported complete (DPWH)

Start Date

April 23, 2021

Target End

February 11, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.